Project 20AH0055

DPWH infrastructure contract
Contract ID:
20AH0055
Fingerprint:
c0bbfa644012cf…11682cb44c Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Feb 12, 2020 (6 yrs 9 mo ago) · Target/actual end Aug 10, 2020
Description:
CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. BANTOCALING, MANGATAREM, PANGASINAN
Category:
Buildings and Facilities
Implementing office:
Contractor:
ST. ALMERS CONSTRUCTION AND ENTERPRISE · DPWH contractor code 42876
Contract amount:
₱2,880,900.00 (₱2.9M)
Funding source:
Regular Infra - GAA 2020 LP
Budget year:
2020

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
5591083c4c06…Jan 31, 2020DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - PANGASINAN 2ND₱2,880,900.00

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25AH0135Jun 11, 2025CONSTRUCTION OF DRAINAGE CANAL IN BARANGAY BOGTONG SILAG, MANGATAREM, PANGASINANCompleted₱9.6M
25AH0160Jun 11, 2025CONSTRUCTION OF MULTI-PURPOSE GYM, POBLACION, MANGATAREM, PANGASINANCompleted₱5.8M
25A00501May 27, 2025BASIC INFRASTRUCTURE PROGRAM (BIP) - CLUSTER II, CONSTRUCTION OF MULTI - PURPOSE BUILDING (1. BRGY POBLACION, AGUILAR, PANGASINAN; 2. BRGY PANGASCASAN, BUGALLON, PANGASINAN; 3. BRGY SONSON ONGKIT, MANGATAREM, PANGASINAN)On-Going₱28.8M
25AH0097Mar 26, 2025CONSTRUCTION(COMPLETION) OF BRIDGE, BARANGAY PACALAT, MANGATAREM, PANGASINANOn-Going₱2.9M
25AH0090Mar 20, 2025CONST'N./IMPRV'T.OF ACCESS ROAD LEADING TO KANDING AND TIMMANGUYOB FALLS,BRGY.CABALUYAN 2ND-BRGY.CACCompleted₱14.4M
25AH0093Mar 17, 2025INSTALLATION/APPLICATION OF ROAD SAFETY FACILITIES(OFF-CARRIAGEWAY IMPRV'T.PAVEMENT MARKINGS,ROAD SICompleted₱3.6M
25AH0100Mar 17, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT),BARANGAY PONGLO MUELAG, MANGATAREM, PANGASINAOn-Going₱8.7M
25AH0082Feb 24, 2025WIDENING OF PERMANENT BRIDGES AT CARPIO BR.(B00674LZ)ALONG PANGASINAN-TARLAC RD.(PHASE II),MANGATAREOn-Going₱38.4M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.