Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 20BE0076

DPWH infrastructure contract
Contract ID:
20BE0076
Fingerprint:
591f3650873426…87b5309956 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Sep 28, 2020 (6 yrs 1 mo ago) · Target/actual end Jan 25, 2021
Description:
CONSTRUCTION OF EVACUATION CENTER BARANGAY CANIOGAN, STO. TOMAS, ISABELA
Category:
Buildings and Facilities
Implementing office:
Contractor:
KWA CONSTRUCTION · DPWH contractor code 43185
Contract amount:
₱4,701,641.00 (₱4.7M)
Funding source:
Regular Infra - GAA 2020 LP
Budget year:
2020

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
eeb9f355a37d…Sep 15, 2020DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - ISABELA 1ST DEO₱4,701,641.00

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25BE0168Jun 17, 2026CONSTRUCTION OF CLASSROOMS, CANDANUM INTEGRATED SCHOOL, CABAGAN, ISABELAOn-Going₱28.5M
25BE0143Jan 22, 2026CONCRETING OF SITIO PELO, BRGY. CANSAN FMR, BRGY. CANSAN, CABAGAN, ISABELAOn-Going₱14.5M
25BE0131Sep 16, 2025CONSTRUCTION OF SCHOOL BUILDING, CUBAG INTEGRATED SCHOOL, BARANGAY CUBAG, CABAGAN, ISABELACompleted₱19.3M
24BE0183Aug 20, 2025CONSTRUCTION OF SEWAGE TREATMENT PLANT, MILAGROS ALBANO DISTRICT HOSPITAL, CABAGAN, ISABELA BARANGAY NGARAG, CABAGAN, ISABELAOn-Going₱28.1M
25BE0078Jul 14, 2025CONVERGENCE AND SPECIAL SUPPORT PROGRAM- BASIC INFRASTRUTURE PROGRAM (BIP) - BIP - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - REHABILITATION OF ROAD, BARANGAY AGGUB, CABAGAN, ISABELAOn-Going₱9.6M
25BE0082Jul 14, 2025CONCRETING OF MALASI-SAN ANTONIO FMR, BRGY. SITIO MALASI, BRGY. SAN ANTONIO, CABAGAN, ISABELAOn-Going₱14.5M
25BE0089Jul 14, 2025CONVERGENCE AND SPECIAL SUPPORT PROGRAM - SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - SIPAG - FLOOD MITIGATION STRUCTURES PROTECTING MAJOR / STRATEGIC PUBLIC BUILDINGS / FACILITIES - CONSTRUCTION OF SLOPE PROTECTION WORKS ALONG CAGAYANOn-Going₱140.3M
25BE0090Jul 14, 2025ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF SLOPE PROTECTION STRUCTUROn-Going₱93.6M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.