Project 20BF0003
DPWH infrastructure contract
Contract ID:
20BF0003
Fingerprint:
63fccb8982ab21…dfd4fe856b Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Dec 3, 2020 (5 yrs 11 mo ago) · Target/actual end Jan 29, 2021
Description:
ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION/ REHABILITATION/ RECONSTRUCTION OF NATIONAL ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - TERTIARY ROADS - GAMU-ROXAS RD (S00783LZ) - K0404 + 100 - K0404
Category:
Roads
Implementing office:
DPWH Isabela 2nd DEO · Region II
Contractor:
RRC CO. INC. (FORMERLY: R R C CONSTRUCTION) · DPWH contractor code 24369
Contract amount:
₱14,394,712.63 (₱14.4M)
Funding source:
Regular Infra - GAA 2020 OO-1
Budget year:
2020
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 26BF0002 | Jun 15, 2026 | ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: ASSET PRESERVATION REHABILITATION/ RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED ROADS TERTIARY ROAD - GAMU-ROXAS RD - K0405 + 744 - K0406 + 039, K0408 + 262 - K0408 + 411, BURGOS, ISAB | Completed | ₱7.5M |
| 25BF0108 | Oct 20, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING , BARANGAY CULLALABO DEL SUR, BURGOS, ISABELA | Completed | ₱16.3M |
| 25BF0082 | Jul 9, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. SAN ROQUE, BURGOS, ISABELA | On-Going | ₱4.8M |
| 25BF0063 | Jun 16, 2025 | OO2:FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES DRAINAGE SYSTEMS -CONSTRUCTION OF BUGNAY CREEK FLOOD CONTROL PROJECT, DALIG SECTION, BURGOS, ISABELA | On-Going | ₱140.4M |
| 25BF0027 | Jun 9, 2025 | COMPLETION OF MULTI-PURPOSE BUILDING, BRGY. SAN MIGUEL, BURGOS, ISABELA | On-Going | ₱4.9M |
| 25BF0026 | Mar 17, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY CALIGUIAN, BURGOS, ISABELA | Completed | ₱4.9M |
| 25BF0030 | Mar 17, 2025 | CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY DIVISORIA, AURORA, ISABELA | Completed | ₱3.0M |
| 24BF0122 | Oct 14, 2024 | RAINWATER COLLECTOR SYSTEM, 1. SAN ROQUE ELEMENTARY SCHOOL, BURGOS, ISABELA, 2. SAN BONIFACIO ELEMENTARY SCHOOL, BURGOS, ISABELA, 3. SIMIMBAAN INTEGRATED SCHOOL, ROXAS, ISABELA, 4. DIVISORIA ELEMENTARY SCHOOL, AURORA, ISABELA, 5. MACUGAY ELEMENTARY SCHOO | Completed | ₱2.9M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.