Project 20CB0017
DPWH infrastructure contract
Contract ID:
20CB0017
Fingerprint:
a341d8e7a2ae77…06598bce54 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Dec 2, 2020 (5 yrs 11 mo ago) · Target/actual end Apr 8, 2021
Description:
CONSTRUCTION/ UPGRADING/ REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS - SECONDARY ROADS - GOV JJ LINAO RD - KO129+(-219) - KO129+154, BATAAN 2ND DISTRICT
Category:
Roads
Implementing office:
DPWH Bataan 2nd DEO · Region III
Contractor:
JEPA CONSTRUCTION & SUPPLIES · DPWH contractor code 30375
Contract amount:
₱10,231,004.25 (₱10.2M)
Funding source:
Regular Infra - GAA 2020 OO-1
Budget year:
2020
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| c70658f0ac11… | Nov 25, 2020 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - BATAAN 2ND DEO | ₱10,231,004.25 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25CB0113 | Jan 5, 2026 | CONSTRUCTION OF SCHOOL BUILDING, PILAR ELEMENTARY SCHOOL, BARANGAY POBLACION, PILAR, BATAAN | On-Going | ₱19.4M |
| 25CB0061 | Aug 15, 2025 | REHABILITATION OF MULTI-PURPOSE BUILDING (COVERED COURT) IN BARANGAY BANTAN, ORION, BATAAN | On-Going | ₱5.0M |
| 25CB0124 | Jul 7, 2025 | REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANSLIDE - TERTIARY ROADS - MT SAMAT RD - K0140 + 261 - K0140 + 341, BATAAN 2ND DISTRICT | On-Going | ₱94.5M |
| 25CB0107 | Jun 16, 2025 | CONSTRUCTION OF MULTI-PURPOSE FACILITY (PHASE 2), BARANGAY PANILAO, PILAR, BATAAN | On-Going | ₱19.4M |
| 25CB0112 | May 28, 2025 | CONCRETING OF BRGY. NAGWALING-DIWA FMR, BRGY. NAGWALING TO BRGY. DIWA, PILAR, BATAAN | Completed | ₱14.9M |
| 25CB0077 | May 27, 2025 | REHABILITATION OF MULTI-PURPOSE BUILDING (PABLO ROMAN NATIONAL HIGH SCHOOL COVERED COURT) IN BARANGAY PANILAO, PILAR, BATAAN | Completed | ₱4.8M |
| 25CB0080 | May 27, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING AT DR. VICTORIA B. ROMAN HIGH SCHOOL, PANTINGAN, PILAR, BATAAN | Completed | ₱9.7M |
| 25CB0083 | May 27, 2025 | REHABILITATION OF MULTI-PURPOSE BUILDING (COVERED COURT) IN BARANGAY PANILAO, PILAR, BATAAN | On-Going | ₱18.4M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.