Project 20CC0111
DPWH infrastructure contract
Contract ID:
20CC0111
Fingerprint:
8e7e3ec93fb3c3…880a8f221d Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Nov 23, 2020 (5 yrs 11 mo ago) · Target/actual end Mar 8, 2021
Description:
REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS - PRIMARY ROADS - MANILA NORTH ROAD (LZ) K0029+000 - K0029+200 BALAGTAS, BULACAN
Category:
Roads
Implementing office:
DPWH Bulacan 1st DEO · Region III
Contractor:
G.D.L. CONSTRUCTION · DPWH contractor code 22796
Contract amount:
₱17,446,694.91 (₱17.4M)
Funding source:
Regular Infra - GAA 2020 OO-1
Budget year:
2020
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25C00499 | Jun 16, 2025 | BRIDGE PROGRAM-RETROFITTING/STRENGTHENING OF PERMANENT BRIDGES-UGONG BRIDGE (BO1987LZ) ALONG MANILA NORTH ROAD, PROVINCE OF BULACAN | Completed | ₱16.2M |
| 25CC0385 | May 23, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING (TRAINING CENTER), HAGONOY, BULACAN | On-Going | ₱19.3M |
| 25CC0406 | May 23, 2025 | REHABILITATION OF UGONG CREEK (LEFT SIDE) BALAGTAS, BULACAN (PACKAGE G) | On-Going | ₱95.0M |
| 25CC0490 | May 23, 2025 | CONSTRUCTION OF REINFORCED CONCRETE RIVER PROTECTION ALONG BALAGTAS RIVER, BARANGAY SAN JUAN, PUROK 1, BALAGTAS, BULACAN (PACKAGE D) | On-Going | ₱95.0M |
| 25C00473 | Apr 8, 2025 | ASSET PRESERVATION PROGRAM-REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS-PRIMARY ROADS-MANILA NORTH ROAD, PROVINCE OF BULACAN | On-Going | ₱135.1M |
| 25CC0433 | Apr 8, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, PLAZA BIGAA, BARANGAY BOROL 1ST, BALAGTAS, BULACAN | On-Going | ₱14.5M |
| 25CC0200 | Mar 21, 2025 | CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY HALL, BARANGAY BOROL 2ND, BALAGTAS, BULACAN | On-Going | ₱4.9M |
| 25CC0236 | Mar 21, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING AT BARANGAY SAN JUAN, BALAGTAS, BULACAN | On-Going | ₱14.5M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.