Project 20CE0003
DPWH infrastructure contract
Contract ID:
20CE0003
Fingerprint:
797b194a6cfeb3…b5739d6e35 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Feb 18, 2020 (6 yrs 8 mo ago) · Target/actual end Nov 13, 2020
Description:
CONSTRUCTION OF FLOOD CONTROL STRUCTURES ALONG RIO CHICO RIVER, BRGY. MACAMIAS, GUIMBA, NUEVA ECIJA
Category:
Flood Control and Drainage
Implementing office:
DPWH Nueva Ecija 1st DEO · Region III
Contractor:
BIG BERTHA CONSTRUCTION & DEVELOPMENT (3191) / NIÑAS CONSTRUCTION CORP. (FORMERLY: NINA'S CONSTRUCTION AND SUPPLIES) · DPWH contractor code 40082
Contract amount:
₱48,998,900.15 (₱49.0M)
Funding source:
Regular Infra - GAA 2020 OO-2
Budget year:
2020
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 24CE0362 | Jun 9, 2025 | CONSTRUCTION OF BRIDGE, BARANGAY CAVITE TO BARANGAY STA. ANA, GUIMBA, NUEVA ECIJA | Completed | ₱104.4M |
| 24CE0363 | Jun 9, 2025 | CONSTRUCTION OF BRIDGE, BARANGAY BALBALINO, GUIMBA, NUEVA ECIJA | Completed | ₱83.7M |
| 25CE0287 | Jun 9, 2025 | CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BRGY. BALBALINO, GUIMBA, NUEVA ECIJA | Completed | ₱5.1M |
| 25CE0323 | Jun 9, 2025 | CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BRGY. SAN ROQUE, GUIMBA, NUEVA ECIJA | Completed | ₱3.9M |
| 25CE0324 | Jun 9, 2025 | CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BRGY. ST. JOHN, GUIMBA, NUEVA ECIJA | Completed | ₱4.9M |
| 25CE0298 | Jun 2, 2025 | CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BRGY. BACAYAO, GUIMBA, NUEVA ECIJA | Completed | ₱3.9M |
| 25CE0299 | Jun 2, 2025 | CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BRGY. CABARUAN, GUIMBA, NUEVA ECIJA | Completed | ₱3.9M |
| 25CE0300 | Jun 2, 2025 | CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BRGY. MACATCATUIT, NUEVA ECIJA | Completed | ₱3.0M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.