Project 20CE0061
DPWH infrastructure contract
Contract ID:
20CE0061
Fingerprint:
46d28a29f988e4…a26d023963 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Oct 19, 2020 (6 yrs ago) · Target/actual end Dec 17, 2020
Description:
CONCRETING OF ROAD, BRGY. CASULUCAN, STO. DOMINGO, NUEVA ECIJA
Category:
Roads
Implementing office:
DPWH Nueva Ecija 1st DEO · Region III
Contractor:
XP BUILDERS · DPWH contractor code 34917
Contract amount:
₱2,969,232.39 (₱3.0M)
Funding source:
Regular Infra - GAA 2020 LP
Budget year:
2020
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 3f4ab5a1125e… | Oct 1, 2020 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - NUEVA ECIJA 1ST DE | ₱2,851,206.73 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25CE0355 | Dec 3, 2025 | CONSTRUCTION OF SCHOOL HEALTH FACILITIES, MUNOZ CS, SCIENCE CITY OF MUÑOZ, NUEVA ECIJA | Completed | ₱4.9M |
| 25CE0302 | Jul 30, 2025 | CONSTRUCTION OF CLASSROOM BUILDING AT CENTRAL LUZON STATE UNIVERSITY, MUNOZ, NUEVA ECIJA | Completed | ₱19.7M |
| 25CE0203 | Jul 9, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY LICAONG, SCIENCE CITY OF MUÑOZ, NUEVA ECIJA | Completed | ₱5.9M |
| 25CE0204 | Jul 1, 2025 | CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, MALIGAYA ES, BARANGAY MALIGAYA, SCIENCE CITY OF MUÑOZ, NUEVA ECIJA | Completed | ₱3.0M |
| 25CE0206 | Jul 1, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY SAN FELIPE, SCIENCE CITY OF MUÑOZ, NUEVA ECIJA | Completed | ₱4.9M |
| 25CE0213 | Jul 1, 2025 | REPLACEMENT OF BOX CULVERT ALONG MUNOZ-TALUGTUG ROAD, BARANGAY CALISITAN, MUÑOZ, NUEVA ECIJA | Completed | ₱11.6M |
| 25CE0205 | Jun 30, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY SAN ANTONIO, SCIENCE CITY OF MUÑOZ, NUEVA ECIJA | Completed | ₱5.9M |
| 25CE0218 | Jun 30, 2025 | CONSTRUCTION OF WATER SYSTEM, BARANGAY VILLA ISLA, SCIENCE CITY OF MUÑOZ, NUEVA ECIJA | On-Going | ₱4.4M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.