Project 20CG0182
DPWH infrastructure contract
Contract ID:
20CG0182
Fingerprint:
46082378c5ae4e…1ca61041ac Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Sep 21, 2020 (6 yrs 1 mo ago) · Target/actual end Nov 4, 2020
Description:
LOCAL INFRASTRUCTURE PROGRAM: MULTIPURPOSE/ FACILITIES - CONSTRUCTION OF MULTI-PURPOSE COVERED AREA WITH REINFORCED CONCRETE SLAB, STA. LUTGARDA, MACABEBE, PAMPANGA
Category:
Buildings and Facilities
Implementing office:
DPWH Pampanga 1st DEO · Region III
Contractor:
MARVERIC BUILDERS · DPWH contractor code 17102
Contract amount:
₱1,879,613.00 (₱1.9M)
Funding source:
Regular Infra - GAA 2020 LP
Budget year:
2020
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 20ce5132eab1… | Sep 10, 2020 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - PAMPANGA 1ST DEO | ₱1,879,613.00 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25CG0176 | Jun 24, 2025 | CONCRETING OF CADUANG TETE TO BRGY. SAPLAD DAVID FARM-TO-MARKET ROAD, BRGY. CADUANG TETE AND BRGY. SAPLAD DAVID, MACABEBE PAMPANGA | Completed | ₱4.7M |
| 25CG0087 | May 22, 2025 | BASIC INFRASTRUCTURE PROGRAM (BIP): ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF ROAD WITH SLOPE PROTECTION WORKS, SITIO PENA, BARANGAY SUA, MASANTOL, PAMPANGA | Completed | ₱93.8M |
| 25CG0088 | May 22, 2025 | SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG): FLOOD MITIGATION STRUCTURES PROTECTING MAJOR / STRATEGIC PUBLIC BUIDLINGS / FACULTIES - REHABILITATION OF FLOOD CONTROL STRUCTURE ALONG PAMPANGA RIVER (PHASE I) AT BARANGAY CONSUELO, MACABEBE, | On-Going | ₱140.3M |
| 25CC0297 | Mar 21, 2025 | CONSTRUCTION OF REVETMENT AT BARANGAY SANTA LUCIA, CALUMPIT, BULACAN | On-Going | ₱37.7M |
| 25CG0025 | Feb 28, 2025 | FLOOD MANAGEMENT PROGRAM: CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG PAMPANGA RIVER, (DOWNSTREAM- RIGHT BANK) BARANGAY CONSUELO, MACABEBE, PAMP | Completed | ₱46.5M |
| 25CG0029 | Feb 21, 2025 | FLOOD MANAGEMENT PROGRAM: CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - REHABILITATION OF ERODED PROTECTION DIKE ALONG PAMPANGA RIVER, BARANGAY CONSUELO, MACABEBE, PAMPANGA | On-Going | ₱93.2M |
| 25CC0123 | Feb 10, 2025 | REHABILITATION OF ROAD, BARANGAY MEYTO, CALUMPIT, BULACAN | Completed | ₱9.7M |
| 24CG0308 | Sep 13, 2024 | BASIC INFRASTRUCTURE PROGRAM (BIP): MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION/ REHABILITATION OF MULTI-PURPOSE BUILDING, MACABEBE, PAMPANGA | Completed | ₱9.4M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.