FY2026 GAA: ₱6.79T
PisoScan

Project 20CJ0004

DPWH infrastructure contract
Contract ID:
20CJ0004
Fingerprint:
f540315ed6fa1f…f7d731e57b Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Feb 20, 2020 (6 yrs 8 mo ago) · Target/actual end Mar 13, 2020
Description:
FLOOD MANAGEMENT PROGRAM CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS REHABILITATION OF FLOOD CONTROL STRUCTURES ALONG BATACAN RIVER, PIT-AO SECTION (PHASE III), SAN CLEMENTE, TARLAC
Category:
Flood Control and Drainage
Implementing office:
DPWH Tarlac DEO · Region III
Contractor:
GJE BUILDERS CORPORATION · DPWH contractor code 18286
As listed: GJE BUILDERS CORPORATION (FORMERLY: GJE BUILDERS)
Contract amount:
₱12,606,719.20 (₱12.6M)
Funding source:
Regular Infra - GAA 2020 OO-2
Budget year:
2020

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
53a0025a9f48…Jan 30, 2020DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - TARLAC 1ST DEO₱12,606,719.20

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25CJ0270Jun 20, 2025CONSTRUCTION OF DUEG - LABNEY DIVERSION ROAD (SEGMENT 1), MAYANTOC, TARLACOn-Going₱95.3M
25CJ0206Apr 8, 2025REHABILITATION OF SAN CLEMENTE ROAD NETWORK (ANNEX 2), SAN CLEMENTE, TARLACCompleted₱99.0M
25CJ0087Mar 10, 2025ACCESS ROAD LEADING TO DUEG ECOTOURISM NATURE'S PARK, BRGY. MAASIN, SAN CLEMENTE, TARLACCompleted₱45.0M
25CJ0125Feb 11, 2025REPLACEMENT OF PERMANENT WEAK BRIDGES SAN CLEMENTE BR. (B01387LZ) ALONG ROMULO H-WAYCompleted₱99.0M
24CJ0312Apr 26, 2024CONSTRUCTION/ REHABILITATION OF WATER SUPPLY/ SEPTAGE AND SEWERAGE/ RAINWATER COLLECTOR SYSTEMCompleted₱2.9M
24CJ0245Feb 29, 2024CONSTRUCTION OF SAN CLEMENTE-MAYANTOC DIVERSION ROAD (SEGMENT D), TARLACCompleted₱96.5M
24CJ0026Feb 1, 2024CONSTRUCTION OF ROAD, BARANGAY MAASIN, SAN CLEMENTE, TARLACCompleted₱4.9M
24CJ0046Feb 1, 2024CONSTRUCTION OF ROAD, BARANGAY CASIPO, SAN CLEMENTE, TARLACCompleted₱4.8M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.