Project 20DE0180
DPWH infrastructure contract
Contract ID:
20DE0180
Fingerprint:
6a50bb2b62a991…9a0de67013 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Mar 2, 2021 (5 yrs 8 mo ago) · Target/actual end Jun 21, 2021
Description:
CONCRETING OF BRGY. SAN ANTONIO FMR, BRGY. SAN ANTONIO, SAN LUIS, BATANGAS
Category:
R.A. 11494 DA FMR 2020
Implementing office:
DPWH Batangas 2nd DEO · Region IV-A
Contractor:
GREENFIELD CONSTRUCTION CORPORATION (FORMERLY:GREENFIELD CONSTRUCTION) · DPWH contractor code 31101
Contract amount:
₱19,900,000.00 (₱19.9M)
Funding source:
Outside Infra - R.A. 11494 DA FMR 2020
Budget year:
2020
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25DE0182 | Jun 9, 2025 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), PUBLIC WATER SUPPLY SYSTEM, CONSTRUCTION (COMPLETION) OF WATER SYSTEM INCLUDING GENERATOR SET AT BARANGAY LOCLOC, SAN LUIS, BATANGAS | Completed | ₱4.8M |
| 25DE0079 | May 26, 2025 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), PUBLIC WATER SUPPLY SYSTEM, CONSTRUCTION OF WATER SUPPLY SYSTEM (WATER WORKS), BARANGAY ABIACAO, SAN LUIS, BATANGAS | On-Going | ₱4.8M |
| 25DE0089 | May 26, 2025 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION/REHABILITATION OF MULTI-PURPOSE BUILDING (COVERED COURT) SAN MARTIN, SAN LUIS BATANGAS | Completed | ₱4.8M |
| 25DE0125 | May 26, 2025 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (COVERED COURT) AT BRGY. TUNGAL, SAN LUIS, BATANGAS | Completed | ₱9.6M |
| 25DE0128 | May 26, 2025 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (COVERED COURT) AT BARANGAY CALUMPANG WEST, SAN LUIS, BATANGAS | Completed | ₱14.8M |
| 25DE0095 | May 20, 2025 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, IMPROVEMENT OF ROAD, DULANGAN-TALON-ABIACAO | Completed | ₱144.8M |
| 25DE0096 | May 20, 2025 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, IMPROVEMENT OF ROAD, MANGGAHAN-SAN MARTIN-S | Completed | ₱144.8M |
| 25DE0097 | May 20, 2025 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, IMPROVEMENT OF ROAD, BAGONG TUBIG-SAN ISIDR | Completed | ₱144.8M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.