Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 20DF0090

DPWH infrastructure contract
Contract ID:
20DF0090
Fingerprint:
d2df171355d65a…d8dfff2ded Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Oct 18, 2020 (6 yrs ago) · Target/actual end Jan 28, 2021
Description:
ORGANIZATIONAL OUTCOME 1, ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, NETWORK DEVELOPMENT PROGRAM, ROAD WIDENING, PRIMARY ROADS, NOVELETA-ROSARIO DIV. RD., K0027+(-120) - K0027+(-004.60)
Category:
Flood Control: Construction - Slope Protection using Structural Measures (e.g., Revetment, Retaining Structures, Rock Netting, Concrete Crib, Shotcrete, MSE Walls, Gabions, Riprap, Masonry), Roads: Construction - PCCP
Implementing office:
DPWH Cavite 1st DEO · Region IV-A
Contractor:
EMSYM CONSTRUCTION CORP. · DPWH contractor code 45094
Contract amount:
₱4,314,940.00 (₱4.3M)
Funding source:
Regular Infra - Flood Control: Construction - Slope Protection using Structural Measures (e.g., Revetment, Retaining Structures, Rock Netting, Concrete Crib, Shotcrete, MSE Walls, Gabions, Riprap, Masonry), Roads: Construction - PCCP
Budget year:
2020

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25DF0183Aug 6, 2025CONVERGENCE AND SPECIAL SUPPORT PROGRAMBASIC INFRASTRUCTURE PROGRAM (BIP)BIP - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICESCONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY PASONG KAWAYAN II, GENERAL TRIAS CITY, CAVITEOn-Going₱14.4M
25DF0129Mar 31, 2025CONVERGENCE AND SPECIAL SUPPORT PROGRAM BASIC INFRASTRUCTURE PROGRAM (BIP) BIP - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), BARANGAY PARADAHAN I, TANZA, CAVITECompleted₱5.8M
25DF0111Mar 27, 2025ORGANIZATIONAL OUTCOME 2 : PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS FLOOD MANAGEMENT PROG CONST/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES & DRAINAGE SYSTEMSCONST OF RD DIKE ALONG PASONG BALITE RIVER, CAVITE GOV CENTER, PHASE 4, BRGY SAN AGUSTOn-Going₱114.6M
25DF0112Mar 27, 2025ORGANIZATIONAL OUTCOME 2 : PROTECT LIVES & PROPERTIES AGAINST MAJOR FLOODS FLOOD MANAGEMENT PROGRAMCONST/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES & DRAINAGE SYSTEMSCONST OF RD DIKE ALONG PASONG BALITE RIVER, CAVITE GOV CENTER, PH 3,BRGY SAN AGUSTINOn-Going₱114.6M
25DF0113Mar 27, 2025ORGANIZATIONAL OUTCOME 2 : PROTECT LIVES & PROPERTIES AGAINST MAJOR FLOODSFLOOD MANAGEMENT PROGCONST/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES & DRAINAGE SYSTEMSCONST OF ROAD DIKE ALONG PASONG BALITE RIVER, CAVITE GOVERNMENT CENTER, PH 2, BRGY SANOn-Going₱119.4M
25DF0007Mar 20, 2025ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEMNETWORK DEVELOPMENT PROGRAMROAD WIDENING - PRIMARY ROADSJUANITO R. REMULLA, SR. RD - K0041 + 929 - K0042 + 118, K0042 + 148 - K0042 + 300, K0043 + 093 - K0043 + 355On-Going₱19.4M
25DF0008Mar 20, 2025ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM ASSET PRESERVATION PROGRAM CONST/ UPGRADING / REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS - PRIMARY ROADS TANZA-TRECE MARTIRES CITY-INDANG RD - K0043 + 600 - K0044+280Completed₱22.1M
25DF0009Mar 20, 2025ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEMASSET PRESERVATION PROGRAMPREVENTIVE MAINTENANCE - PRIMARY ROADSTANZA-TRECE MARTIRES CITY-INDANG RD - K0046 + 189 - K0046 + 761Completed₱22.2M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.