Project 20DN0089
DPWH infrastructure contract
Contract ID:
20DN0089
Fingerprint:
a653570614f125…3eb9a012bc Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Aug 19, 2020 (6 yrs 2 mo ago) · Target/actual end Jan 15, 2021
Description:
REHABILITATION OF ROAD WITH DRAINAGE SYSTEM, RAINBOW VILLAGE, BRGY. KALAYAAN, ANGONO, RIZAL
Category:
Roads
Implementing office:
DPWH Rizal 1st DEO · Region IV-A
Contractor:
MONTEONE CONSTRUCTION CORPORATION · DPWH contractor code 32353
Contract amount:
₱10,563,176.51 (₱10.6M)
Funding source:
Regular Infra - GAA 2020 LP
Budget year:
2020
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 3e87b522b896… | Aug 5, 2020 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - RIZAL 1ST ED | ₱10,563,176.51 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25DN0085 | May 28, 2025 | REHABILITATION OF ROAD, BARANGAY KALAYAAN, ANGONO, RIZAL (FIRST DISTRICT) | On-Going | ₱9.6M |
| 25DN0086 | May 28, 2025 | CONSTRUCTION OF ROAD, DOÑA AURORA STREET, BARANGAY POBLACION IBABA, ANGONO, RIZAL (FIRST DISTRICT) | On-Going | ₱9.9M |
| 25DN0049 | Apr 8, 2025 | CONSTRUCTION OF FLOOD CONTROL STRUCTURE, ANGONO RIVER, BARANGAY SAN VICENTE, ANGONO, RIZAL (FIRST DISTRICT) | Completed | ₱49.0M |
| 25DN0046 | Apr 7, 2025 | CONSTRUCTION OF FLOOD CONTROL STRUCTURE, BANGIAD CREEK, TAYTAY, RIZAL (FIRST DISTRICT) | On-Going | ₱18.8M |
| 24DN0146 | Jul 29, 2024 | CONSTRUCTION OF MULTI-PURPOSE BUILDING (ANGONO ART CENTER WITHIN THE ANGONO LAKESIDE ECOPARK), BARANGAY SAN VICENTE ANGONO, RIZAL (FIRST DISTRICT) | On-Going | ₱9.6M |
| 24D00242 | Jul 19, 2024 | CONSTRUCTION OF DRAINAGE ALONG LAKESHORE, BARANGAY KALAYAAN, ANGONO, RIZAL | On-Going | ₱56.6M |
| 24DN0168 | Jul 15, 2024 | IMPROVEMENT OF ROAD AND DRAINAGE SYSTEM, IBAÑEZ ST., BARANGAY SAN ISIDRO, BARANGAY STO. NIÑO AND BARANGAY SAN VICENTE ANGONO, RIZAL (FIRST DISTRICT) | On-Going | ₱68.5M |
| 24DN0145 | Jun 25, 2024 | CONSTRUCTION OF DRAINAGE SYSTEM, FLORENTINO ST., BRGY. KALAYAAN ANGONO, RIZAL (FIRST DISTRICT) | Completed | ₱7.9M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.