Project 20DN0137
DPWH infrastructure contract
Contract ID:
20DN0137
Fingerprint:
12e7348eb838f2…26ce473dcb Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Nov 26, 2020 (5 yrs 11 mo ago) · Target/actual end Mar 25, 2021
Description:
CONSTRUCTION/IMPROVEMENT OF CLIFFSIDE AND ROAD WIDENING WITH DRAINAGE SYSTEM, BRGY. MACAMOT, BINANGONAN, RIZAL
Category:
Roads
Implementing office:
DPWH Rizal 1st DEO · Region IV-A
Contractor:
D.R. ROBLES CONSTRUCTION · DPWH contractor code 28559
Contract amount:
₱9,652,384.86 (₱9.7M)
Funding source:
Regular Infra - GAA 2020 LP
Budget year:
2020
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| fd5b065d2eb6… | Nov 20, 2020 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - RIZAL 1ST ED | ₱9,652,384.86 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25DN0097 | Jun 26, 2025 | ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - NETWORK DEVELOPMENT PROGRAM - ROAD WIDENING - SECONDARY ROADS - MANILA EAST RD - K0033+276 - K0033+551, RIZAL (FIRST DISTRICT) | On-Going | ₱7.1M |
| 25DN0098 | May 29, 2025 | CONSTRUCTION OF ROAD AT BARANGAY ITHAN TO BARANGAY KALINAWAN, BINANGONAN, RIZAL (FIRST DISTRICT) | On-Going | ₱19.0M |
| 25DN0101 | May 29, 2025 | CONSTRUCTION OF FLOOD STRUCTURE, CREEK, W. CERRERO GOING TO F. CEQUEÑA, BARANGAY MACAMOT, BINANGONAN, RIZAL (FIRST DISTRICT) | Completed | ₱9.5M |
| 25DN0106 | May 29, 2025 | CONSTRUCTION OF BOX CULVERT CONNECTING BARANGAY JANOSA AND BARANGAY KAYTOME BINANGONAN, RIZAL (FIRST DISTRICT) | On-Going | ₱4.9M |
| 25DN0112 | May 29, 2025 | FY 2025 CONVERGENCE AND SPECIAL SUPPORT PROGRAM - RAINWATER COLLECTOR SYSTEM BINANGONAN, RIZAL (FIRST DISTRICT) | On-Going | ₱2.6M |
| 25DN0067 | May 27, 2025 | CONSTRUCTION OF ROAD AT CABLE WAY GOING TO KASINAY, BARANGAY MACAMOT AND BARANGAY DARANGAN, BINANGONAN, RIZAL (FIRST DISTRICT) | Completed | ₱67.5M |
| 25DN0044 | May 26, 2025 | CONSTRUCTION OF FLOOD CONTROL STRUCTURE, SAN JUAN CREEK, BINANGONAN, RIZAL (FIRST DISTRICT) | Completed | ₱19.6M |
| 25DN0056 | May 26, 2025 | CONSTRUCTION OF BREAKWATER, BARANGAY KALINAWAN GOING TO BARANGAY PIPINDAN, BINANGONAN, RIZAL (FIRST DISTRICT) | On-Going | ₱9.5M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.