Project 20DQ0119

DPWH infrastructure contract
Contract ID:
20DQ0119
Fingerprint:
519f31b76c8594…c04a7f57be Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Sep 14, 2020 (6 yrs 1 mo ago) · Target/actual end Feb 10, 2021
Description:
LOCAL PROGRAM - LOCAL INFRASTRUCTURE PROGRAM - BUILDINGS AND OTHER STRUCTURES - MULTIPURPOSE/FACILITIES - CONSTRUCTION OF MULTI-PURPOSE BUILDING AND OTHER IMPROVEMENTS AT SPRINGVILLE EXECUTIVE AT MOLINO 3, BACOOR, CAVITE
Category:
Buildings and Facilities
Implementing office:
DPWH Cavite 3rd DEO · Region IV-A
Contractor:
EMSYM CONSTRUCTION CORP. · DPWH contractor code 45094
Contract amount:
₱4,847,977.74 (₱4.8M)
Funding source:
Regular Infra - GAA 2020 LP
Budget year:
2020

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25DQ0110Jul 3, 2025CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY MALIKSI 2, BACOOR CITY, CAVITEOn-Going₱9.8M
25DQ0111Jul 3, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY BAYANAN, BACOOR CITY, CAVITEOn-Going₱9.8M
25DF0158Jul 1, 2025CONVERGENCE AND SPECIAL SUPPORT PROGRAMBASIC INFRASTRUCTURE PROGRAM (BIP)ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITESCONSTRUCTION OF ROAD WITH DRAINAGE AT BRGY. PALICO IV, CITY OF IMUS,On-Going₱4.8M
25DQ0084Jun 17, 2025CONSTRUCTION OF RIVERWALL AND OTHER IMPROVEMENT WORKS ALONG BACOOR RIVER, PHASE 1, CITY OF BACOOR, CAVITEOn-Going₱96.0M
25DQ0085Jun 17, 2025CONSTRUCTION OF RIVERWALL AND OTHER IMPROVEMENT WORKS ALONG BACOOR RIVER, PHASE 2, CITY OF BACOOR, CAVITEOn-Going₱98.0M
25DQ0090Jun 17, 2025CONSTRUCTION OF SLOPE AND BANKS PROTECTION WORKS ALONG BACOOR RIVER, CITY OF BACOOR, CAVITE (PHASE 1)On-Going₱98.0M
25DQ0099Jun 17, 2025CONSTRUCTION OF SLOPE AND BANKS PROTECTION WORKS ALONG BACOOR RIVER, CITY OF BACOOR, CAVITE (PHASE 3)On-Going₱98.0M
25DQ0101Jun 17, 2025CONSTRUCTION OF SLOPE AND BANKS PROTECTION WORKS ALONG BACOOR RIVER, CITY OF BACOOR, CAVITE (PHASE 2)On-Going₱98.0M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.