Project 20EI0186
DPWH infrastructure contract
Contract ID:
20EI0186
Fingerprint:
8e5e3ecf8d94af…0cea618bce Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Oct 12, 2020 (6 yrs 1 mo ago) · Target/actual end Jun 23, 2021
Description:
CONCRETING OF ROAD, PANGGULAYAN - ANOLING - BULI, PINAMALAYAN, ORIENTAL MINDORO
Category:
Contingent Fund 2019 Extended
Implementing office:
DPWH Southern Mindoro DEO · MIMAROPA Region
Contractor:
LUMEL GLENN CONSTRUCTION · DPWH contractor code 26817
Contract amount:
₱38,599,674.21 (₱38.6M)
Funding source:
Outside Infra - Contingent Fund 2019 Extended
Budget year:
2019
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 7ff43720d941… | Sep 14, 2020 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - SOUTHERN MINDORO D | ₱37,286,064.40 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 26EI0052 | Aug 25, 2026 | CONSTRUCTION / UPGRADING/ REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS - SECONDARY ROADS - CALAPAN SOUTH RD - K0071+ 766 - K0072 + 178, K0072 + 191 - K0074 + 252, K0074 + 550 - K0075 + 252, K0075 + 318 - K0075 + 949, PINAMALAYAN - GLORIA, ORIENTAL | On-Going | ₱103.4M |
| 25EI0162 | Jul 18, 2025 | CONSTRUCTION OF ORIENTAL MINDORO CENTRAL DISTRICT HOSPITAL, PINAMALAYAN, ORIENTAL MINDORO | Terminated | ₱0 |
| 25EI0164 | Jun 16, 2025 | COMPLETION (CONSTRUCTION) OF MULTI-PURPOSE BUILDING AT BRGY. ANOLING, PINAMALAYAN, ORIENTAL MINDORO, PHASE II | Completed | ₱2.9M |
| 25EI0165 | Jun 16, 2025 | COMPLETION (CONSTRUCTION) OF MULTI-PURPOSE BUILDING AT BRGY. PALAYAN, PINAMALAYAN, ORIENTAL MINDORO PHASE II | Completed | ₱2.9M |
| 25ED0129 | May 16, 2025 | RETROFITTING/STRENGTHENING OF PULA BRIDGE, PULA, SOCORRO, ORIENTAL MINDORO | Completed | ₱43.6M |
| 25EI0143 | Apr 8, 2025 | SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-CONSTRUCTION OF ROAD, MARAYOS-SABANG, PINAMALAYAN, ORIENTAL MINDORO | On-Going | ₱14.5M |
| 25E00122 | Apr 6, 2025 | SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- COASTAL ROADS TO AUGMENT RESILIENCY OF COASTYAL COMMUNITIES- CONST. OF COASTAL ROAD/SHORE PROTECTION ALONG BRGY. ZONE III-BRGY. QUINABIGAN, PINAMALAYAN, OR. MINDORO | On-Going | ₱231.0M |
| 25E00123 | Apr 6, 2025 | SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- COASTAL ROADS TO AUGMENT RESILIENCY OF COASTAL COMMUNITIES- CONST. OF COASTAL ROAD/SHORE PROTECTION ALONG BRGY. ZONE III, STA. 000+290-STA. 000+620; STA. 000+660-STA. 000+813.50, PINAMALAYAN, O | On-Going | ₱230.8M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.