Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 20FB0063

DPWH infrastructure contract
Hashed input (canonical JSON of the source row)
["dpwh","20FB0063","FLOOD CONTROL STRUCTURES/FACILITIES: CONSTRUCTION OF FLOOD CONTROL SYSTEM ALONG TALADONG RIVER, TALADONG, CAMALIG, ALBAY","Flood Control and Drainage","Completed",52360662.57,0,100,"Albay 2nd DEO","Region V","JEJAN CONSTRUCTION AND SUPPLY(FOR. JEJAN CONSTRUCT (34712) / STEVEN CONSTRUCTION & SUPPLY (21987)","2020-02-28","2020-09-22",2020,"Regular Infra - GAA 2020 LP",13.13662,123.65761,"500502000","500500000"]
SHA-256
8478ffca3b75d5edcf628692871d036400bf483143708a2b77e28fa70218a35c

Hash the line above with SHA-256 to reproduce the fingerprint. It proves the record is unchanged since import. It is not a blockchain entry, and it cannot prove the source data is accurate.