FY2026 GAA: ₱6.79T
PisoScan

Project 20FE0017

DPWH infrastructure contract
Contract ID:
20FE0017
Fingerprint:
95028337718f27…123f33bdc7 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Mar 3, 2020 (6 yrs 8 mo ago) · Target/actual end Oct 15, 2020
Description:
OO2: FLOOD MANAGEMENT - CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF REVETMENT (ALONG BICOL RIVER) WITHIN BICOL RIVER BASIN, BRGY. ALIMBUYOG, MILAOR, CAMARINES SUR
Category:
Flood Control and Drainage
Implementing office:
Contractor:
BICOL GOLDROCK CONSTRUCTION CORPORATION · DPWH contractor code 32376
Contract amount:
₱45,401,000.00 (₱45.4M)
Funding source:
Regular Infra - GAA 2020 OO-2
Budget year:
2020

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25FF0054Sep 2, 2025CSSP;BASIC INFRA PROGRAM(BIP)-ACCESS ROADS & OR BRIDGES FROM THE NATIONAL ROAD LEADING TO MAJOR/STRATEGIC PUBLIC BUILDING FACILITIES-CONST OF ROADS WITH SLOPE PROTECTION WORKS OF PORO -SAN JOSE EAST -SAN JOSE WEST CANAMAN CAMARINES SUROn-Going₱146.4M
25FF0053Aug 22, 2025CONCRETING OF BRGY, SAN FRANCISCO TO BRGY. IQUIN FMR, BRGY, SAN FRANCISCO CANAMAN CAMARINES SURCompleted₱14.7M
25F00030Apr 10, 2025ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS-CONSTRUCTION OF FLOOD MITIGATION STRUCTURE, BICOCompleted₱147.6M
25FF0012Apr 4, 2025CSSP;SUSTAINABLE INFRASTRUCTURE PROJECTS ELEVATING GAPS(SIPAG)- ACCESS ROAD & 0R BRIDGES FROM THE NATIONAL ROADS LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS -FACILITIES CONST OF ROAD BRGY MANGAYAWAN TO BRGY SAN FRANCISCO CANAMAN CAMARINES SUROn-Going₱82.6M
25FF0023Mar 26, 2025BIP;FLOOD MITIGATION STRUCTURE PROTECTING PUBLIC INFRA./FACILITIES-CONST. OF FLOOD MITIGATION STRUCTURE ZONE 6 BARANGAY SAN FRANCISCO CANAMAN CAMARINES SURCompleted₱8.6M
25F00024Mar 12, 2025ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-CONSTRUCTION OF FLOOD MITIGATION STRUCTURE, INAGYANAN RIVER, PACKAGE 1, BARANOn-Going₱146.7M
25F00151Feb 28, 2025ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS-CONSTRUCTION OF FLOOD MITIGATION STRUCTURE, BICOOn-Going₱144.9M
24F00057Sep 12, 2024ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-NETWORK DEVELOPMENT PROGRAM-CONSTRUCTION OF BY-PASS AND DIVERSION ROADS-NAGA-JCT. MAGARAO-CANAMAN-LIBMANAN JCT. PPH ROAD (SKYBRIDGE), CAMARINES SUR PACKAGE 2, MAGARAO, CAMARINES SUR (On-Going₱273.7M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.