Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 20GA0030

DPWH infrastructure contract
Contract ID:
20GA0030
Fingerprint:
2e97fa8575e9e6…66395c3f97 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Feb 24, 2020 (6 yrs 8 mo ago) · Target/actual end Oct 4, 2021
Description:
CONST. (COMPLETION) OF EVACUATION CENTER, BRGY. ALFONSO XII, LIBACAO, AKLAN
Category:
Buildings and Facilities
Implementing office:
DPWH Aklan DEO · Region VI
Contractor:
FIRST MAKEEN CONSTRUCTION · DPWH contractor code 32352
Contract amount:
₱1,922,000.00 (₱1.9M)
Funding source:
Regular Infra - GAA 2020 LP
Budget year:
2020

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
88c6a17ce239…Feb 19, 2020DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - AKLAN DEO₱1,922,000.00

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25GA0135Aug 20, 2025CONCRETING OF BRGY. AGMAILIG FMR, BRGY. AGMAILIG, LIBACAO, AKLANOn-Going₱14.9M
25GA0053Apr 3, 2025CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (COVERED COURT) BARANGAY CALAMCAN, LIBACAO, AKLANOn-Going₱2.5M
25GA0060Apr 3, 2025CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (COVERED COURT/ EVACUATION CENTER), BARANGAY CALACABIAN, LIBACAO, AKLANOn-Going₱2.5M
25GA0063Mar 19, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY SIBALEW, LIBACAO, AKLANOn-Going₱4.9M
25GA0055Feb 26, 2025CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (COVERED COURT), BARANGAY OGSIP, LIBACAO, AKLANOn-Going₱2.0M
25GA0058Feb 26, 2025CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (COVERED COURT), SITIO AGBATUAN, BARANGAY OYANG, LIBACAO, AKLANOn-Going₱3.0M
25GA0062Feb 26, 2025CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY CASIT-AN, LIBACAO, AKLANOn-Going₱2.5M
25G00008Feb 14, 2025CONSTRUCTION OF MAGUGBA BRIDGE, BARANGAY POBLACION, LIBACAO, AKLANOn-Going₱192.6M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.