Project 20GA0063
DPWH infrastructure contract
Contract ID:
20GA0063
Fingerprint:
29ed550ec595f0…7ad55e1725 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Sep 28, 2020 (6 yrs 1 mo ago) · Target/actual end Nov 19, 2021
Description:
AKLAN RIVER FLOOD CONTROL PROJECT, LEZO, AKLAN
Category:
Flood Control and Drainage
Implementing office:
DPWH Aklan DEO · Region VI
Contract amount:
₱61,143,840.66 (₱61.1M)
Funding source:
Regular Infra - GAA 2020 OO-2
Budget year:
2020
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25GA0115 | May 23, 2025 | CONSTRUCTION/COMPLETION OF MULTI-PURPOSE BUILDING, BARANGAY BUGASONGAN, LEZO, AKLAN | On-Going | ₱2.0M |
| 25G00040 | Mar 6, 2025 | KALIBO CIRCUMFERENTIAL ROAD (MAKATO- LEZO SECTION), AKLAN | On-Going | ₱48.0M |
| 24GA0217 | Sep 10, 2024 | CONSTRUCTION OF 2STY8CL, LEZO IS, LEZO AKLAN | On-Going | ₱23.5M |
| 24GA0037 | May 28, 2024 | REHABILITATION OF ROAD, BARANGAY STA. CRUZ BIGA-A, LEZO, AKLAN | On-Going | ₱4.9M |
| 24GA0153 | Apr 23, 2024 | CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, POBLACION, LEZO, AKLAN | On-Going | ₱4.9M |
| 24G00003 | Feb 8, 2024 | KALIBO CIRCUMFERENTIAL ROAD (MAKATO- LEZO SECTION), AKLAN | On-Going | ₱193.0M |
| 24GA0044 | Feb 7, 2024 | CONSTRUCTION (COMPLETION) OF MPB BRGY. BAGTO, LEZO, AKLAN | Completed | ₱2.0M |
| 24GA0058 | Feb 7, 2024 | CONSTRUCTION (COMPLETION) OF MPB BRGY. IBAO, LEZO, AKLAN | Completed | ₱2.0M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.