FY2026 GAA: ₱6.79T
PisoScan

Project 20GD0107

DPWH infrastructure contract
Contract ID:
20GD0107
Fingerprint:
d4bba17702af35…e679a0e20c Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Jul 12, 2020 (6 yrs 4 mo ago) · Target/actual end Aug 10, 2020
Description:
CONSTRUCTION/REHABILITATION OF WATER SUPPLY/SEPTAGE/SEWERAGE/RAIN WATER COLLECTORS
Category:
Water Provision and Storage
Implementing office:
DPWH Capiz 1st DEO · Region VI
Contractor:
KERGEL BUILDERS · DPWH contractor code 44923
Contract amount:
₱3,465,585.20 (₱3.5M)
Funding source:
Regular Infra - GAA 2020 CSSP
Budget year:
2020

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25GD0060Jul 8, 2025WIDENING OF BRIDGE - ANHAWON BR. (B00244PN) ALONG ILOILO EAST COAST-CAPIZ RD (PHASE II)On-Going₱37.0M
25GD0035Jun 9, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY BAGACAY, PANAY, CAPIZOn-Going₱9.9M
25GD0041Jun 9, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANAGY BINANTU-AN, PANAY, CAPIZOn-Going₱4.9M
25GD0036Apr 14, 2025CONSTRUCTION OF FLOOD MITIGATION STRUCTURES - CONSTRUCTION OF FLOOD MITIGATION FACILITIES ALONG PANAY/MAMBUSAO RIVER BASIN, TICO RIVER CONTROL, PANAY, CAPIZOn-Going₱29.0M
25GD0001Mar 24, 2025CONSTRUCTION OF FLOOD MITIGATION STRUCTURES - CONSTRUCTION OF RIVER CONTROL ALONG PANAY RIVER, BARANGAY COGON, PANAY, CAPIZOn-Going₱142.9M
25GD0003Mar 17, 2025CONSTRUCTION OF FLOOD MITIGATION STRUCTURE - CONSTRUCTION OF FLOOD MITIGATION FACILITIES ALONG PANAY/MAMBUSAO RIVER BASIN, TALASA RIVER CONTROL, BRGY, TALASA, PANAY, CAPIZOn-Going₱56.3M
25GD0016Mar 17, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY TANZA NORTE, PANAY, CAPIZCompleted₱4.9M
24GD0065Oct 21, 2024CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY BINANGIG, PANAY, CAPIZCompleted₱8.0M