Project 20GI0090
DPWH infrastructure contract
Contract ID:
20GI0090
Fingerprint:
f0e53994aac78a…04555f06b7 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Aug 14, 2020 (6 yrs 3 mo ago) · Target/actual end Feb 12, 2021
Description:
CONCRETING OF SITIO BANGLID, BRGY CONSOLACION FMR, BRGY CONSOLACION, SAN MIGUEL, ILOILO
Category:
Roads
Implementing office:
DPWH Iloilo 4th DEO · Region VI
Contractor:
1 BEATUS BUILDERS CORP. · DPWH contractor code 43709
Contract amount:
₱11,934,988.51 (₱11.9M)
Funding source:
Outside Infra - GAA 2020 DA FMR
Budget year:
2020
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 465f0b1e1e80… | Jul 29, 2020 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - ILOILO 4TH DEO | ₱11,934,991.95 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 26G00027 | Jun 8, 2026 | ILOILO CIRCUMFERENTIAL ROAD 3, SAN MIGUEL, ILOILO STA. 5+941.25 - STA. 6+168.25 | On-Going | ₱44.8M |
| 25G00082 | May 21, 2025 | ILOILO CIRCUMFERENTIAL RD 3, ILOILO | On-Going | ₱95.0M |
| 25GI0071 | May 20, 2025 | CONSTRUCTION OF AGANAN FLOOD CONTROL STRUCTURE JARO-AGANAN RIVER), BARANGAY 6, SAN MIGUEL, ILOILO | Completed | ₱19.7M |
| 25GI0042 | Mar 25, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY IGTAMBO, SAN MIGUEL, ILOILO | Completed | ₱4.9M |
| 25GI0013 | Mar 17, 2025 | ACCESS ROAD FROM THE NATIONAL ROAD, BRGY. SAN ANTONIO-BRGY. STO. ANGEL, SAN MIGUEL - BRGY. BAGUINGIN-LANOT, ALIMODIAN LEADING TO GODUCATE, SAN MIGUEL, ILOILO | On-Going | ₱19.5M |
| 25GI0004 | Feb 18, 2025 | CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, SAN MIGUEL, ILOILO | Completed | ₱3.7M |
| 25GI0007 | Feb 18, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY SANTO NINO, SAN MIGUEL, ILOILO | Completed | ₱4.9M |
| 24GI0022 | May 24, 2024 | PREVENTIVE MAINTENANCE OF ROAD: ASPHALT OVERLAY - MANDURRIAO-SN MIGUEL-ALIMODIAN-MAASIN-CABATUAN RD - K0018 + 400 - K0021 + 040 | Completed | ₱94.1M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.