Project 20GL0043
DPWH infrastructure contract
Contract ID:
20GL0043
Fingerprint:
b5268a9d9d4a59…697dbb2d2b Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Feb 16, 2020 (6 yrs 8 mo ago) · Target/actual end Dec 29, 2020
Description:
ACCESS ROAD LEADING TO KAITULARI ECOPARK, MOISES PADILLA, NEGROS OCCIDENTAL
Category:
Roads
Implementing office:
DPWH Negros Occidental 2nd DEO · Negros Island Region
Contractor:
SILVERGRACES CONSTRUCTION & CONSTRUCTION SUPPLY · DPWH contractor code 36158
As listed: SILVERGRACES CONSTRUCTION AND CONSTRUCTION SUPPLY
Contract amount:
₱24,499,076.68 (₱24.5M)
Funding source:
Regular Infra - GAA 2020 CSSP
Budget year:
2020
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| d93754b8a6bc… | Jan 31, 2020 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - NEG. OCC. 2ND DEO | ₱23,274,875.55 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25GL0103 | Jun 3, 2025 | PREVENTIVE MAINTENANCE OF ROAD: ASPHALT OVERLAY - JCT BAGONAWA-LA CASTELLANA-ISABELA RD - K0071 + 000 - K0072 + 244 | On-Going | ₱47.3M |
| 25GL0121 | Mar 25, 2025 | CONCRETING OF BRGY. MACAGAHAY FMR, BRGY. MACAGAHAY, MOISES PADILLA, NEGROS OCCIDENTAL | Completed | ₱29.8M |
| 25GL0135 | Mar 25, 2025 | CONSTRUCTION OF ROAD AT SO. CAN-AMO, BARANGAY 6, MOISES PADILLA, NEGROS OCCIDENTAL | Completed | ₱9.6M |
| 25GL0069 | Mar 19, 2025 | ACCESS ROAD LEADING TO KAITULARI ECOPARK, MOISES PADILLA, NEGROS OCCIDENTAL | Completed | ₱9.7M |
| 25GL0085 | Mar 19, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY 3, MOISES PADILLA, NEGROS OCCIDENTAL | Completed | ₱4.9M |
| 25GL0044 | Feb 25, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY MACAGAHAY, MOISES PADILLA, NEGROS OCCIDENTAL | Completed | ₱4.9M |
| 25GL0046 | Feb 25, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY INOLINGAN, MOISES PADILLA, NEGROS OCCIDENTAL | Completed | ₱4.9M |
| 25GL0068 | Feb 25, 2025 | CONSTRUCTION OF ROAD, SITIO ARUM, BARANGAY MACAGAHAY, MOISES PADILLA, NEGROS OCCIDENTAL | On-Going | ₱9.7M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.