FY2026 GAA: ₱6.79T
PisoScan

Project 20GO0009

DPWH infrastructure contract
Hashed input (canonical JSON of the source row)
["dpwh","20GO0009","CONSTRUCTION OF FLOOD CONTROL STRUCTURE, BRGY. PAHANOCOY, PHASE 2, BACOLOD CITY","Flood Control and Drainage","Completed",34300000,0,100,"Bacolod City DEO","Negros Island Region","SUPREME ABF CONST. & CONST. SUPPLY COMPANY INC. (25226)","2020-11-25","2021-06-08",2020,"Regular Infra - GAA 2020 OO-2",10.61896,122.92794,"1830200000","1804500000"]
SHA-256
24e11e8c1a68c91eedd224d0f7975115c4430718c2740edf8f844f2cb302b493

Hash the line above with SHA-256 to reproduce the fingerprint. It proves the record is unchanged since import. It is not a blockchain entry, and it cannot prove the source data is accurate.