Project 20HA0078
DPWH infrastructure contract
Contract ID:
20HA0078
Fingerprint:
350360d6c56520…1a85e353d1 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Nov 27, 2020 (5 yrs 11 mo ago) · Target/actual end Mar 1, 2022
Description:
REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - JCT (TNR) CORTES-BALILIHAN-CATIGBIAN-MACAAS RD - K0012+785-K0012+930, K0013+540-K0013+573, K0017+175-K0017+240, K0041+684-K0041+790, K0045+279-K0045+600, K0046+420-K0046+49
Category:
Roads
Implementing office:
DPWH Bohol 1st DEO · Region VII
Contractor:
EC SOLICON BUILDERS & SUPPLY, INC. · DPWH contractor code 37545
Contract amount:
₱46,783,200.00 (₱46.8M)
Funding source:
Regular Infra - GAA 2020 OO-1
Budget year:
2020
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| d7989b146fd3… | Nov 24, 2020 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - BOHOL 1ST ED | ₱46,783,200.00 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25HA0123 | Feb 13, 2026 | CONSTRUCTION OF MULTI-PURPOSE BUILDING (GOVERNMENT CENTER), MALAYO SUR, CORTES, BOHOL | On-Going | ₱99.0M |
| 24HA0160 | May 15, 2025 | CONSTRUCTION OF FLOOD MITIGATION STRUCTURES AT BARANGAY MALAYO NORTE TO BARANGAY LORETO ALONG ABATAN RIVER, CORTES, BOHOL | On-Going | ₱96.0M |
| 25HA0047 | May 15, 2025 | CONSTRUCTION OF ROAD, MALAYO SUR, CORTES, BOHOL | Completed | ₱9.8M |
| 25HA0095 | May 15, 2025 | RIHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - TERTIARY ROADS - JCT (TNR) CORTES-BALILIHAN-CATIGBIAN-MACAAS RD - K0010+299 - K0010+323, K0014+798 - K0014 + 855, K0015 + 028 - K0015 + 050, K0015 + 291 - K0015 + 384, K00 | Completed | ₱4.5M |
| 25H00035 | Apr 11, 2025 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES, CONSTRUCTION OF FLOOD CONTROL STRUCTURE (PHASE II), VIGA, ANTEQUERA, BOHOL | On-Going | ₱101.2M |
| 25HA0051 | Mar 27, 2025 | CONSTRUCTION OF FATIMA BRIDGE, BARANGAY FATIMA, CORTES, BOHOL | Completed | ₱11.8M |
| 25HA0027 | Feb 10, 2025 | REHABILITATION OF DPWH AREA EQUIPMENT SERVICE BUILDING, DE LA PAZ, CORTES, BOHOL | Completed | ₱19.6M |
| 25HA0039 | Feb 10, 2025 | INSTALLATION/ APPLICATION OF ROAD SAFETY FACILITIES (ROADWAY LIGTHING) ALONG THE PRESIDENT CARLOS P. GACIA CIRCUMFERENTIAL RD - K0010+434 - K0010+676, K0011+000 - K0013+500, K0014+000 - K0014+400, K0014+740 - K0016+680, K0017+000 - K0018+000, K0018+450 - | Completed | ₱38.2M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.