Project 20HB0169
DPWH infrastructure contract
This contract as an OC4IDS project record, the infrastructure standard used by OpenGovChain. Download: JSON
{
"id": "oc4ids-pisoscan-dpwh-20HB0169",
"title": "CONCRETING OF SITIO TAWID, BRGY. MAYUGA TO BRGY. BIABAS FMR, MAYUGA AND BRGY. BIABAS, GUINDULMAN, BOHOL STA.0+954.55 - STA.1+068.00; STA.1 +840.00 - STA.1+943.86; STA.2+082.15 -STA.2+251.81; STA.2+637.81 -STA.2+808.27",
"sector": [
"Flood Control: Construction - Drainage (e.g., Closed and Open Conduits, Spillway), Roads: Construction - PCCP"
],
"status": "completed",
"publicAuthority": {
"name": "DPWH Bohol 3rd DEO"
},
"period": {
"startDate": "2020-09-10",
"endDate": "2021-02-11"
},
"budget": {
"amount": {
"amount": 11464970.18,
"currency": "PHP"
}
},
"locations": [
{
"geometry": {
"type": "Point",
"coordinates": [
124.42235,
9.79113
]
}
}
],
"parties": [
{
"name": "N.N. YU CONSTRUCTION, INC.",
"roles": [
"supplier"
]
}
],
"contractingProcesses": [
{
"id": "20HB0169",
"summary": {
"title": "CONCRETING OF SITIO TAWID, BRGY. MAYUGA TO BRGY. BIABAS FMR, MAYUGA AND BRGY. BIABAS, GUINDULMAN, BOHOL STA.0+954.55 - STA.1+068.00; STA.1 +840.00 - STA.1+943.86; STA.2+082.15 -STA.2+251.81; STA.2+637.81 -STA.2+808.27",
"status": "closed",
"contractValue": {
"amount": 11464970.18,
"currency": "PHP"
}
}
}
],
"pisoscan": {
"dpwhStatus": "Completed",
"physicalProgressPercent": 100,
"fundingSource": "Outside Infra - Flood Control: Construction - Drainage (e.g., Closed and Open Conduits, Spillway), Roads: Construction - PCCP",
"sourceDataset": "DPWH contract list via BetterGov.ph",
"sha256": "2832b6c9a7267f1683574b63fa78a4ae123bbb9a9813463cda4af4be2d931ea1"
}
}