FY2026 GAA: ₱6.79T
PisoScan

Project 20HD0104

DPWH infrastructure contract
Contract ID:
20HD0104
Fingerprint:
c8d7c81181b3de…5862626b74 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Feb 26, 2021 (5 yrs 8 mo ago) · Target/actual end Apr 27, 2021
Description:
CONCRETING OF BARANGAY MUABOG FMR, BARANGAY MUABOG, TABOGON, CEBU
Category:
Roads
Implementing office:
DPWH Cebu 4th DEO · Region VII
Contractor:
BANTAY CONSTRUCTION · DPWH contractor code 35290
Contract amount:
₱9,614,318.40 (₱9.6M)
Funding source:
Outside Infra - R.A. 11494 DA FMR 2020
Budget year:
2020

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25HG0084Jun 9, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY ILIHAN, TABOGON, CEBUOn-Going₱14.6M
25HG0066May 19, 2025CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY TABA-AO, TABOGON, CEBUCompleted₱4.9M
25HG0067May 19, 2025CONSTRUCTION OF (NEW) MULTI-PURPOSE BUILDING, BARANGAY LABANGON, TABOGON, CEBUCompleted₱4.9M
25HG0079May 19, 2025CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY ILIHAN, TABOGON, CEBUCompleted₱4.9M
25HG0078Mar 28, 2025CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY ILIHAN, TABOGON, CEBUCompleted₱4.9M
25HG0073Mar 27, 2025CONCRETING OF SITIO COLONIA, BRGY. ILIHAN FMR, BRGY. ILIHAN, TABOGON, CEBUCompleted₱14.5M
25HG0004Mar 24, 2025ROAD WIDENING - SECONDARY ROADS, CEBU NORTH HAGNAYA WHARF RD - K0079+396 - K0080+220, K0092+435 - K0093+086, TABOGON AND CITY OF BOGO, CEBUCompleted₱48.7M
25HG0003Feb 27, 2025REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - SECONDARY ROADS, CEBU NORTH HAGNAYA WHARF RD - K0078+865 - K0078+963, TABOGON, CEBUCompleted₱24.1M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.