Project 20IA0052
DPWH infrastructure contract
Contract ID:
20IA0052
Fingerprint:
9ec3679d8fdf92…a491413ee6 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Dec 1, 2020 (5 yrs 11 mo ago) · Target/actual end Mar 22, 2021
Description:
REHABILITATION OF CABIBIHAN FLOOD CONTROL ALONG BILIRAN CIR. ROAD
Category:
Flood Control and Drainage
Implementing office:
DPWH Biliran DEO · Region VIII
Contractor:
YOYEN ENTERPRISES · DPWH contractor code 15541
Contract amount:
₱28,980,280.00 (₱29.0M)
Funding source:
Regular Infra - GAA 2020 LP
Budget year:
2020
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| be70fdfe30a5… | Oct 5, 2020 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - BILIRAN ED | ₱28,980,280.00 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 26IA0035 | Jul 22, 2026 | REHABILITATION/MAJOR REPAIR OF PERMANENT BRIDGES - MAPULA BR. (B00046BR) ALONG BILIRAN CIRCUMFERENTIAL RD | On-Going | ₱4.8M |
| 26IA0001 | Jun 16, 2026 | NETWORK DEVELOPMENT - ROAD WIDENING - SECONDARY ROADS - BILIRAN CIRCUMFERENTIAL RD - K1086+940 - K1088+800 | On-Going | ₱69.7M |
| 26IA0006 | May 13, 2026 | NETWORK DEVELOPMENT - ROAD WIDENING - SECONDARY ROADS - BILIRAN CIRCUMFERENTIAL RD - K1083+026 - K1084+018 | On-Going | ₱23.6M |
| 25IA0156 | Jul 15, 2025 | REHABILITATION OF CABIBIHAN-VICTORY ROAD, CAIBIRAN, BILIRAN | On-Going | ₱19.6M |
| 25IA0157 | Jul 15, 2025 | CONSTRUCTION OF ROAD, BRGY. MAURANG, CAIBIRAN, BILIRAN | On-Going | ₱14.7M |
| 25IA0163 | Jul 15, 2025 | CONSTRUCTION OF SEAWALL, SITIO KATIPUNAN, BARANGAY VICTORY, CAIBIRAN, BILIRAN | On-Going | ₱9.8M |
| 25IA0146 | Jun 30, 2025 | CONSTRUCTION OF ROAD, SITIO MALUBAGO, BARANGAY VICTORY, CABIRAN, BILIRAN | On-Going | ₱9.8M |
| 25IA0147 | Jun 30, 2025 | CONSTRUCTION OF ROAD, SITIO KATIPUNAN, BARANGAY VICTORY, CAIBIRAN, BILIRAN | On-Going | ₱9.8M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.