Project 20IB0075

DPWH infrastructure contract
Contract ID:
20IB0075
Fingerprint:
e46f401656c226…3ef1e6a7c1 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Feb 24, 2020 (6 yrs 8 mo ago) · Target/actual end Jun 2, 2020
Description:
CONCRETING OF LOCAL ROAD, SITIO KALAWIT, BRGY. SAN ROQUE, ORAS, EASTERN SAMAR
Category:
Roads
Implementing office:
DPWH Eastern Samar DEO · Region VIII
Contractor:
J.A. DEVELOPERS AND ENGINEERS · DPWH contractor code 43714
Contract amount:
₱3,959,969.48 (₱4.0M)
Funding source:
Regular Infra - GAA 2020 LP
Budget year:
2020

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
316f2fca6b88…Feb 3, 2020DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - EASTERN SAMAR DEO₱3,728,608.06

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25IB0174Dec 8, 2025CONSTRUCTION OF FLOOD CONTROL STRUCTURE, BARANGAY CAMANGA, ORAS, EASTERN SAMAROn-Going₱4.9M
25IB0156Nov 12, 2025CONSTRUCTION OF ROAD, BARANGAY JAPAY, ORAS, EASTERN SAMAROn-Going₱4.9M
25IB0142Aug 26, 2025CONSTRUCTION OF BRIDGE, BARANGAY RIZAL, ORAS, EASTERN SAMARCompleted₱4.9M
25IB0073Jul 30, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY HALL, BARANGAY TAWAGAN, ORAS, EASTERN SAMARCompleted₱4.9M
25IB0051Jun 3, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), BARANGAY GAMOT, ORAS, EASTERN SAMARCompleted₱4.9M
25IB0074Jun 3, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING, SENIOR CITIZEN CENTER, BARANGAY SAN ROQUE, ORAS, EASTERN SAMARCompleted₱4.9M
25IB0093Jun 3, 2025CONSTRUCTION OF EVACUATION CENTER, BARANGAY MALINGON, ORAS, EASTERN SAMARCompleted₱4.9M
25IB0010Feb 25, 2025PREVENTIVE MAINTENANCE SECONDARY ROADS, JCT. TAFT-ORAS-SAN POLICARPO-ARTECHE ROAD, K0914+249 - K0914+334, K0914+488 - K0914+534, K0915+532 - K0915+550, K0915+588 - K0915+605, K0915+597 - K0915+617, K0916+168 - K0916+186, K0916+511 - K0916+530, K0916+552 -Completed₱5.1M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.