Project 20IF0063
DPWH infrastructure contract
Contract ID:
20IF0063
Fingerprint:
600f0bffa79e4d…22694d8152 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Aug 10, 2020 (6 yrs 3 mo ago) · Target/actual end Oct 30, 2020
Description:
CY 2020 BEFF - CONSTRUCTION OF CLASSROOMS, BATCH 2, NAULAYAN ELEMENTARY SCHOOL, MATAG-OB, LEYTE
Category:
Buildings and Facilities
Implementing office:
DPWH Leyte 4th DEO · Region VIII
Contractor:
GBTU CONSTRUCTION AND SUPPLIES · DPWH contractor code 37239
As listed: GBTU CONSTRUCTION AND SUPPLIES (FOR: K.T.U. CONSTRUCTION)
Contract amount:
₱3,959,986.57 (₱4.0M)
Funding source:
Outside Infra - GAA 2020 DepEd BEFF
Budget year:
2020
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25IF0114 | May 4, 2026 | LAST MILE SCHOOLS PROGRAM - MASABA I ELEMENTARY SCHOOL, PALOMPON, LEYTE | On-Going | ₱12.6M |
| 25IF0088 | Jun 19, 2025 | CONCRETING OF BRGY. MALAZARTE - BRGY. CAMBADBAD FMR, BRGY. MALAZARTE AND BRGY. CAMBADBAD, MATAG-OB, LEYTE | On-Going | ₱49.7M |
| 25IF0065 | Mar 26, 2025 | CONSTRUCTION OF ROAD, SITIO CAMANSI, BARANGAY STA. ROSA, MATAG-OB, LEYTE | On-Going | ₱24.0M |
| 25IF0019 | Mar 4, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY CANDELARIA, MATAG-OB, LEYTE | Completed | ₱9.8M |
| 25IF0006 | Feb 21, 2025 | CONSTRUCTION OF FLOOD CONTROL MITIGATION STRUCTURE, BARANGAY RIVERSIDE, MATAG-OB, LEYTE | On-Going | ₱48.2M |
| 25IF0028 | Feb 21, 2025 | CONSTRUCTION (COMPLETION) OF ROAD - BARANGAY MANLILINAO - BARANGAY SAN SEBASTIAN, ORMOC CITY | Completed | ₱48.9M |
| 25IF0035 | Feb 20, 2025 | CONSTRUCTION OF CONCRETE ROAD, BARANGAY CACAO, KANANGA, LEYTE | Completed | ₱5.9M |
| 24I00268 | Jan 13, 2025 | CONSTRUCTION OF NEW SUPER HEALTH CENTERS/RHU - MATAG-OB SUPER HEALTH CENTER, LEYTE, MATAG-OB, LEYTE | On-Going | ₱11.9M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.