Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 20J00025

DPWH infrastructure contract
Contract ID:
20J00025
Fingerprint:
68e15191451ecc…cb4141ea03 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Feb 21, 2020 (6 yrs 8 mo ago) · Target/actual end Nov 25, 2020
Description:
CONSTRUCTION OF BYPASS/DIVERSION ROADS - BALIGUIAN COASTAL ROAD, JCT. BALIGUIAN - KAUSWAGAN - MAMAD SECTION, ZAMBOANGA DEL NORTE (PACKAGE 1)
Category:
Roads
Implementing office:
DPWH Region IX · Region IX
Contractor:
ESR CONSTRUCTION & DEVELOPMENT CORPORATION · DPWH contractor code 10451
As listed: ESR CONSTRUCTION AND DEVELOPMENT CORPORATION (FORMERLY: ESR CONSTRUCTION & SUPPLIES)
Contract amount:
₱144,750,000.00 (₱144.8M)
Funding source:
Regular Infra - GAA 2020 OO-1
Budget year:
2020

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
dd75f59697aa…Feb 18, 2020DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - REGION IX₱144,272,860.21

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25JJ0047Apr 4, 2025CONSTRUCTION OF RAINWATER COLLECTOR SYSTEM (RWCS) AT (1) KAUSWAGAN ELEMENTARY SCHOOL, BALIGUIAN, ZN (2) BALIGUIAN CENTRAL SCHOOL, BALIGUIAN, ZN (3) S. CABRAL ELEMENTARY SCHOOL, SIOCON, ZN (4) SIBUCO CENTRAL SCHOOL, SIBUCO, ZN (5) SIRAWAI CENTRAL SCHOOL,On-Going₱2.6M
25JJ0004Mar 27, 2025REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - SECONDARY ROADS, LILOY-SIOCON RD - K2064 + 728 - K2064 + 757, K2064 + 939 - K2064 + 972Completed₱13.4M
25JJ0008Mar 27, 2025REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - SECONDARY ROADS, LILOY-SIOCON RD - K2056 + 892 - K2056 + 942Completed₱24.7M
25JJ0009Mar 27, 2025REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - SECONDARY ROADS, LILOY-SIOCON RD - K2028 + 110 - K2028 + 124, K2029 + 560 - K2029 + 620, K2030 + 013 - K2030 + 043, K2030 + 452 - K2030 + 494, K2030 + 527 - K2030 + 552Completed₱38.0M
25JJ0010Mar 27, 2025REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - SECONDARY ROADS, LILOY-SIOCON RD - K2031 + 208 - K2031 + 235, K2031 + 847 - K2031 + 882Completed₱16.4M
25JJ0016Mar 27, 2025PAVING OF UNPAVED ROADS - SECONDARY ROADS, LILOY-SIOCON RD - K2049 + 500 - K2051 + 800Completed₱76.7M
25JJ0018Mar 27, 2025PAVING OF UNPAVED ROADS - SECONDARY ROADS, LILOY-SIOCON RD - K2040 + 250 - K2040 + 896On-Going₱21.9M
25JJ0019Mar 27, 2025PAVING OF UNPAVED ROADS - SECONDARY ROADS, LILOY-SIOCON RD - K2053 + 600 - K2054 + 300On-Going₱24.9M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.