Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 20JB0005

DPWH infrastructure contract
Contract ID:
20JB0005
Fingerprint:
1fc684e64faf46…01f65ee725 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Feb 20, 2020 (6 yrs 8 mo ago) · Target/actual end Mar 27, 2022
Description:
CONSTRUCTION OF SCHOOL BUILDING IN MOLITON NATIONAL HIGH SCHOOL - PANAMPALAY EXTENSION, PANAMPALAY, PRES. MANUEL ROXAS, ZAMBOANGA DEL NORTE
Category:
Buildings and Facilities
Implementing office:
Contractor:
MORTE CONSTRUCTION · DPWH contractor code 24515
Contract amount:
₱1,979,896.75 (₱2.0M)
Funding source:
Regular Infra - GAA 2020 LP
Budget year:
2020

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
8f811fef37b0…Feb 5, 2020DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - ZAMBOANGA DEL NORT₱1,979,896.75

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25JC0087Sep 25, 2025CONSTRUCTION OF MULTI PURPOSE BUILDING- COMPLETION OF OF MULTI PURPOSE BUILDING INCLUDING FACILITIES (PAWIKAN RESCUE AND HATCHERY CENTER) BRGY. DOHINOB, PRES. MANUEL ROXAS, ZAMBOANGA DEL NORTEOn-Going₱2.4M
25JC0050Jul 7, 2025CONSTRUCTION OF DRAINAGE STRUCTURE ALONG ROAD - DIPOLOG - SINDANGAN - LILOY RD - K1857+640.00 - K1858+091.00On-Going₱9.5M
25JC0086Jul 7, 2025CONSTRUCTION OF MULTI PURPOSE BUILDING- COMPLETION OF MULTI-PURPOSE BUILDING (MINI COVERED COURT) SEBOD ELEMENTARY SCHOOL, BRGY. SEBOD, PRES. MANUEL ROXAS, ZAMBOANGA DEL NORTECompleted₱2.4M
25JC0055Jun 5, 2025ROAD WIDENING - DIPOLOG-SINDANGAN-LILOY RD - K1861+760 - K1863+660On-Going₱103.9M
25JC0088May 29, 2025COMPLETION OF HOME ECONOMICS BUILDING, VILLAHERMOSO ELEMENTARY SCHOOL, BRGY. VILLA HERMOSO, PRES. MANUEL ROXAS, ZAMBOANGA DEL NORTECompleted₱2.4M
24JC0066Jul 26, 2024CONSTRUCTION OF 1-STOREY 2-CLASSROOM SCHOOL BUILDING IN MINANG ELEMENTARY SCHOOL, BARANGAY MINANG, PRES. MANUEL ROXAS, ZAMBOANGA DEL NORTE.Completed₱5.0M
24JC0002Feb 14, 2024CONSTRUCTION OF CONCRETE ROAD - CONSTRUCTION OF ROAD, PRES. MANUEL ROXAS, ZAMBOANGA DEL NORTECompleted₱5.9M
24JC0013Feb 14, 2024CONSTRUCTION OF FLOOD MITIGATION STRUCTURE- CONSTRUCTION OF FLOOD CONTROL STRUCTURE, PRES. MANUEL ROXAS, ZAMBOANGA DEL NORTECompleted₱9.9M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.