Project 20LA0040
DPWH infrastructure contract
Contract ID:
20LA0040
Fingerprint:
23f1878d772945…dde3bae4e0 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Feb 28, 2020 (6 yrs 8 mo ago) · Target/actual end Aug 10, 2020
Description:
CONSTRUCTION OF REVETMENT ALONG KINGKING RIVER AT BALANBAN SECTION (R/S), BRGY. KINGKING, PANTUKAN COMPOSTELA VALLEY PROVINCE
Category:
GAA 2020 OO-2
Implementing office:
DPWH Davao de Oro 1st DEO · Region XI
Contractor:
NUEDA BUILDERS CONSTRUCTION & SUPPLY INC. (39776) / R.A. PAHATI CONST. & SUPPLY, INC. · DPWH contractor code 35843
Contract amount:
₱49,565,436.14 (₱49.6M)
Funding source:
Regular Infra - GAA 2020 OO-2
Budget year:
2020
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 26LA0005 | Apr 30, 2026 | BONGABONG BR. (B00201MN) ALONG SURIGAO-DAVAO COASTAL RD., PANTUKAN, DAVAO DE ORO | On-Going | ₱4.8M |
| 26LA0006 | Apr 27, 2026 | PAGAKPAK BR. (B00200MN) ALONG SURIGAO-DAVAO COASTAL RD., PANTUKAN, DAVAO DE ORO | On-Going | ₱4.8M |
| 25LA0055 | Dec 29, 2025 | CONSTRUCTION OF WATER SUPPLY SYSTEM - LEVEL II, SOUTH SIDE, PANTUKAN, DAVAO DE ORO | On-Going | ₱19.8M |
| 24LA0158 | Nov 25, 2025 | CONSTRUCTION OF PANTUKAN SPORTS COMPLEX PHASE 4, PANTUKAN, DAVAO DE ORO | On-Going | ₱49.0M |
| 25L00161 | Nov 21, 2025 | CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG LAHI RIVER, BARANGAY MAGNAGA, PANTUKAN, DAVAO DE ORO | On-Going | ₱18.7M |
| 24LA0154 | Jun 24, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING (MUNICIPAL HALL) PHASE 4, BARANGAY KINGKING, PANTUKAN, DAVAO DE ORO | On-Going | ₱98.0M |
| 25LA0010 | Jun 20, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY BINUGSAYAN ELEMENTARY SCHOOL, PANTUKAN, DAVAO DE ORO | On-Going | ₱4.9M |
| 25LA0032 | Jun 20, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY NAPNAPAN, PANTUKAN, DAVAO DE ORO | On-Going | ₱4.9M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.