Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 20LD0015

DPWH infrastructure contract
Contract ID:
20LD0015
Fingerprint:
64090be01b2087…6140183e81 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Feb 20, 2020 (6 yrs 8 mo ago) · Target/actual end May 19, 2020
Description:
CONSTRUCTION OF CONCRETE ROAD-ACCESS ROAD LEADING TO SHYREN BUGAK SPRING RESORT & BRIGOLE LAKE, MATANAO, DAVAO DEL SUR
Category:
Roads
Implementing office:
Contractor:
HI-VIEW RESOURCES & DEVELOPMENT CORPORATION · DPWH contractor code 28505
Contract amount:
₱9,800,000.00 (₱9.8M)
Funding source:
Regular Infra - GAA 2020 CSSP
Budget year:
2020

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
1fd1d03dc5f5…Feb 12, 2020DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - DAVAO DEL SUR 1ST₱9,501,513.42

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25LD0193Feb 23, 2026PREVENTIVE MAINTENANCE OF ROAD: ASPHALT OVERLAY- DAVAO- COTABATO ROAD (JCT. DIGOS- COTABATO SECTION)-K1575+035-K1575+322, K1582+670-, K1582+714, K1592+100-K1592+1078, DAVAO DEL SUROn-Going₱94.8M
25LD0202Sep 22, 2025PREVENTIVE MAINTENANCE OF ROAD: ASPHALT OVERLAY-DAVAO-COTABATO RD (JCT DIGOS-COTABATO SECT.)-K1579+093-K1580+625, DAVAO DEL SURCompleted₱95.9M
25LD0203Sep 22, 2025PREVENTIVE MAINTENANCE OF ROAD: ASPHALT OVERLAY- DAVAO- COTABATO ROAD (JCT. DIGOS- COTABATO SECTION)- K1572+000-K1573+032, K1575+322-K1575+565, DAVAO DEL SURCompleted₱96.1M
25LD0157Jun 25, 2025CONSTRUCTION OF FLOOD CONTROL STRUCTURE-CONCRETE REVETMENT AT MATANAO RIVER ALONG MATANAO NHS LEFT SIDE DOWNSTREAM SECTION PHASE I, MATANAO, DAVAO DEL SUROn-Going₱122.8M
25LD0205Jun 3, 2025CONSTRUCTION OF EVACUATION CENTER, BARANGAY SAN VICENTE, MATANAO, DAVAO DEL SURCompleted₱4.8M
25LD0018Mar 26, 2025PREVENTIVE MAINTENANCE OF ROAD; ASPHALT OVERLAY- DAVAO- COTABATO RD (JCT DIGOS-COTABATO SECT)-K1575+565-K1576+140, K1582+714-K1582+844, K1585+241-K1585+700, DAVAO DEL SUROn-Going₱96.3M
25LD0056Mar 26, 2025CONSTRUCTION OF ROAD, CENTRO KIBAO TO PUROK 3, BARANGAY KIBAO, MATANAO, DAVAO DEL SUROn-Going₱19.8M
25LD0206Mar 26, 2025CONCRETING OF BRGY. CAMANCHILES FMR, BRGY. CAMANCHILES, MATANAO, DAVAO DEL SURCompleted₱14.5M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.