Project 20M00010

DPWH infrastructure contract
Contract ID:
20M00010
Fingerprint:
a14af0f7829c39…5745bdb236 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Dec 18, 2020 (5 yrs 10 mo ago) · Target/actual end Apr 21, 2022
Description:
WIDENING OF PERMANENT BRIDGE - CARMEN PARALLEL BR. ALONG BUKIDNON-COTABATO ROAD, K1652+008 - K1652+230.55, CARMEN, NORTH COTABATO
Category:
Bridges
Implementing office:
DPWH Region XII · Region XII
Contractor:
AKN CONSTRUCTION CORPORATION · DPWH contractor code 11845
Contract amount:
₱143,654,309.78 (₱143.7M)
Funding source:
Regular Infra - GAA 2020 OO-1
Budget year:
2020

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
04e229b213d3…Dec 17, 2020DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - REGION XII₱137,511,203.13

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
26MI0060Jun 18, 2026RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE ALONG BUKIDNON-COTABATO RD - K1629 + 530 - K1629 + 625Completed₱53.1M
26MI0007Jun 17, 2026(RE-BID) ASPHALT OVERLAY ALONG BUKIDNON-COTABATO RD - K1611 + 000 - K1611 + 620Completed₱18.7M
26MI0010May 7, 2026ROAD WIDENING ALONG BUKIDNON-COTABATO RD - K1625 + 716 - K1627 + 175On-Going₱40.8M
25MI0030Aug 19, 2025BUKIDNON-COTABATO RD - K1630 + 100 - K1630 + 300Completed₱79.3M
25MI0031Aug 19, 2025BUKIDNON-COTABATO RD - K1629 + 625 - K1629 + 905Completed₱105.6M
25MI0056Aug 19, 2025BUKIDNON-COTABATO RD - K1612+656 - K1613+000On-Going₱127.8M
25MI0089Jul 29, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING (BARANGAY HALL) IN BRGY. UGALINGAN, CARMEN, COTABATOCompleted₱4.7M
25MI0090Jul 29, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING (BARANGAY HALL) IN BRGY. LILIONGAN, CARMEN, COTABATOCompleted₱4.7M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.