Project 20M00050
DPWH infrastructure contract
Contract ID:
20M00050
Fingerprint:
dbc68805f4d3d8…dd60f2e7a9 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Mar 25, 2020 (6 yrs 7 mo ago) · Target/actual end Jan 25, 2021
Description:
CONSTRUCTION OF CONCRETE ROAD - NRJ POBLACION PRESIDENT QUIRINO CONNECTING TO BRGY. BAGUMBAYAN IN SUPPORT OF PALM OIL, MUSCOVADO/SUGARCANE, VEGETABLES, RICE AND CORN, STA, 4+944 - STA. 7+364, PRESIDENT QUIRINO, SULTAN KUDARAT
Category:
GAA 2020 CSSP
Implementing office:
DPWH Region XII · Region XII
Contractor:
Contract amount:
₱106,098,195.02 (₱106.1M)
Funding source:
Regular Infra - GAA 2020 CSSP
Budget year:
2020
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25MG0020 | Apr 11, 2025 | ROAD WIDENING-MIDSAYAP-MARBEL RD-K1774+083-K1774+581 | Completed | ₱9.6M |
| 25MF0031 | Mar 26, 2025 | CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (BARANGAY HALL), BARANGAY BANNAWAG, PRESIDENT QUIRINO, SULTAN KUDARAT | Completed | ₱3.0M |
| 25MF0032 | Mar 26, 2025 | CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (MINI GYM BLEACHERS), BARANGAY BANNAWAG, PRESIDENT QUIRINO, SULTAN KUDARAT | Completed | ₱3.0M |
| 25MG0002 | Feb 28, 2025 | PREVENTIVE MAINTENANCE OF ROAD: ASPHALT OVERLAY-MIDSAYAP-MARBEL RD-K1774+083-K1774+336, SOUH COTABATO | Completed | ₱11.2M |
| 25MG0003 | Feb 28, 2025 | PREVENTIVE MAINTENANCE OF ROAD: ASPHALT OVERLAY-MIDSAYAP-MARBEL RD-K1775+000-K1775+570, SOUTH COTABATO | Completed | ₱38.0M |
| 24M00200 | Jul 29, 2024 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY POBLACION, PRESIDENT QUIRINO, SULTAN KUDARAT | Completed | ₱9.9M |
| 24MF0052 | May 15, 2024 | CONSTRUCTION OF 1-STOREY 2-CLASSROOM SCHOOL BUILDING IN PRESIDENT QUIRINO NATIONAL HIGH SCHOOL, BARANGAY POBLACION, PRESIDENT QUIRINO, SULTAN KUDARAT | Completed | ₱5.0M |
| 24MG0050 | May 15, 2024 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. NEW CUYAPO, TANTANGAN, SOUTH COTABATO | Completed | ₱4.9M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.