Project 20MA0096
DPWH infrastructure contract
Contract ID:
20MA0096
Fingerprint:
56f640602cd9ff…007409427f Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Oct 22, 2020 (6 yrs ago) · Target/actual end Jan 14, 2021
Description:
CONSTRUCTION OF MULTI-PURPOSE BUILDING AT BRGY ZAPAKAN, RAJAHBUAYAN, MAGUINDANAO
Category:
Buildings and Facilities
Implementing office:
DPWH Cotabato City DEO · Region XII
Contractor:
TRIPLE S CONSTRUCTION · DPWH contractor code 44986
Contract amount:
₱2,950,609.80 (₱3.0M)
Funding source:
Regular Infra - GAA 2020 LP
Budget year:
2020
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| fb32aeceecab… | Sep 30, 2020 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - REGION XII - COTAB | ₱2,950,609.80 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 23M00138 | Jun 27, 2023 | CONSTRUCTION OF MULTI-PURPOSE BUILDING (TRAINING CENTER), BARANGAY SAPAKAN, RAJAH BUAYAN, MAGUINDANAO | Completed | ₱6.9M |
| 22M00124 | Dec 5, 2022 | CONSTRUCTION OF MULTI-PURPOSE BUILDING (BAI DAYANG HERITAGE HOUSE): BARANGAY GAUNAN, RAJAH BUAYAN, MAGUINDANAO | Completed | ₱6.8M |
| 21M00105 | Oct 22, 2021 | RE-BLOCKING OF DULAWAN-MIDSAYAP-MAKAR ROAD ALONG RAJAH BUAYAN, MAGUINDANAO K1733+280.5-K1736+380.5 (WITH EXCEPTION), RAJAH BUAYAN, MAGUINDANAO | Completed | ₱33.4M |
| 21MA0013 | Oct 22, 2021 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY BAKAT, RAJAH BUAYAN, MAGUINDANAO | Completed | ₱2.7M |
| 21MA0019 | Oct 22, 2021 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY MALIBPOLOK, RAJAH BUAYAN, MAGUINDANAO | Completed | ₱2.7M |
| 20MA0031 | Feb 24, 2020 | CONCRETING OF ROAD, BRGY. POBLACION, RAJAH BUAYAN, MAGUINDANAO | Completed | ₱9.9M |
| 19MA0110 | Nov 21, 2019 | CONCRETING OF SITIO GUINTAWAN FMR, BRGY. PIDSANDAWAN, MAMASAPANO, MAGUINDANAO | Completed | ₱5.0M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.