Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 20MD0044

DPWH infrastructure contract
Contract ID:
20MD0044
Fingerprint:
4d4e3903815258…bd2c4099c0 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Feb 14, 2020 (6 yrs 9 mo ago) · Target/actual end Jun 3, 2020
Description:
CONSTRUCTION OF CONCRETE ROAD ALONG POBLACION, PIKIT-BATULAWAN-BALATICAN-GOKOTAN BRIDGE IN SUPPORT OF PALM OIL INDUSTRY-UNIVARICH CARMEN PALM OIL MILL (BOI REGISTERED), PIKIT, COTABATO
Category:
Roads
Implementing office:
DPWH Cotabato 1st DEO · Region XII
Contractor:
DQMB CONSTRUCTION & SUPPLY CORP. · DPWH contractor code 42964
Contract amount:
₱9,308,546.55 (₱9.3M)
Funding source:
Regular Infra - GAA 2020 CSSP
Budget year:
2020

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
27556d5ed9c6…Feb 10, 2020DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - NORTH COTABATO 2ND₱9,308,546.55

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
24M00282Jan 15, 2025CONSTRUCTION OF NEW SUPER HEALTH CENTERS/RHU - PIKIT SUPER HEALTH CENTER, NORTH COTABATOOn-Going₱11.9M
24MD0038May 15, 2024ROAD WIDENING - PRIMARY ROAD - ALONG DAVAO-COTABATO RD (JCT DIGOS-COTABATO SECT.), PIKIT, COTABATOCompleted₱78.6M
24MD0017Feb 7, 2024CONSTRUCTION OF DRAINAGE, CALAWAG CREEK, POBLACION, PIKIT, COTABATOCompleted₱4.9M
23MD0062Jun 5, 2023CONSTRUCTION OF SOLAR WATER SYSTEM, BRGY. LADTINGAN, PIKIT, NORTH COTABATOCompleted₱9.7M
23MD0038Feb 28, 2023CONSTRUCTION OF ROAD, POBLACION - LADTINGAN ROAD, PIKIT, NORTH COTABATOCompleted₱4.9M
23MD0040Feb 20, 2023CONSTRUCTION OF ROAD - POBLACION, PIKIT-BATULAWAN - BALATICAN - GOKOTAN BRIDGE IN SUPPORT OF PALM OIL INDUSTRY - UNIVANICH CARMEN PALM OIL MILL ( BOI REGISTERED ), PIKIT, COTABATOCompleted₱9.7M
23MD0041Feb 20, 2023CONSTRUCTION OF DRAINAGE CANAL, POBLACION - CALAWAG CREEK, PIKIT, NORTH COTABATOCompleted₱4.9M
22MD0097Dec 20, 2022CONSTRUCTION/REHABILITATION OF WATER SUPPLY/SEPTAGE AND SEWERAGE/RAINWATER COLLECTOR SYSTEM/RAINWATER COLLECTOR IN PUBLIC FACILITIES (CLUSTER 2) SADAAN ES, MIDSAYAP, CENTRAL GLAD, MIDSAYAP, VILLARICA ES, MIDSAYAP, SAN PEDRO ES, MIDSAYAP, DR. C.H. DELESCompleted₱2.1M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.