Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 20NA0040

DPWH infrastructure contract
Contract ID:
20NA0040
Fingerprint:
34f94f9932d07d…77a699bb15 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Sep 13, 2020 (6 yrs 2 mo ago) · Target/actual end Jul 9, 2021
Description:
CONSTRUCTION OF LEVEL II WATER SYSTEM THROUGH SOLAR PUMP OF BRGY. CALAMBA, CABADBARAN CITY, AGUSAN DEL NORTE
Category:
Water Provision and Storage
Implementing office:
Contract amount:
₱19,582,486.39 (₱19.6M)
Funding source:
Regular Infra - GAA 2020 LP
Budget year:
2020

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25NA0051Mar 19, 2026CONSERVATION AND RESTORATION OF GABALDON AND OTHER HERITAGE SCHOOL BUILDINGS - NORTH CABADBARAN CES, CITY OF CABADBARAN, AGUSAN DEL NORTECompleted₱8.0M
25N00022Sep 15, 2025MAHARLIKA HIGHWAY (AGUSAN-DAVAO SECT)- K1255+492 - K1257+004, K1272+587- K1273+420On-Going₱136.2M
25NA0042Jul 10, 2025(CLUSTER) RAINWATER COLLECTOR SYSTEM, AGUSAN DEL NORTECompleted₱2.6M
25NA0039May 28, 2025CONSTRUCTION OF SCHOOL BUILDING, COMAGASCAS ELEMENTARY SCHOOL, BRGY. COMAGASCAS, CABADBARAN CITY, AGUSAN DEL NORTECompleted₱9.6M
25NA0040May 28, 2025CONSTRUCTION OF SCHOOL BUILDING, CONCEPCION INTEGRATED SCHOOL, BRGY. CONCEPCION, CABADBARAN CITY, AGUSAN DEL NORTECompleted₱8.6M
25N00091Apr 10, 2025CONSTRUCTION OF ROAD, PACKAGE 2, TELESFORA-CAMINGAWAN-CANTICOL, TUBAY, AGUSAN DEL NORTECompleted₱48.9M
25NA0013Mar 24, 2025CONSTRUCTION OF SLOPE PROTECTION STRUCTURE, CALIBUNAN CREEK FROM PUROK 4 TO PUROK 11, BARANGAY CALIBUNAN, CABADBARAN CITY, AGUSAN DEL NORTECompleted₱9.8M
25NA0015Mar 24, 2025CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS, NRJ-COMAGASCAS-DEL PILAR-PIRADA LEADING TO TUNNEL ROAD, BRGY. DEL PILAR, CABADBARAN, AGUSAN DEL NORTECompleted₱24.5M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.