Project 21A00067
DPWH infrastructure contract
Contract ID:
21A00067
Fingerprint:
467d8336395971…1231172d9c Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Mar 8, 2021 (5 yrs 8 mo ago) · Target/actual end Mar 31, 2022
Description:
CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - VIGAN-CABUGAO COASTAL/DIVERSION ROAD, ILOCOS SUR
Category:
Roads
Implementing office:
DPWH Region I · Region I
Contractor:
A.P.B. CONSTRUCTION · DPWH contractor code 17055
Contract amount:
₱96,150,000.00 (₱96.2M)
Funding source:
Regular Infra - GAA 2021 OO-1
Budget year:
2021
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 4b5503491a12… | Feb 15, 2021 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - REGION I | ₱93,529,377.00 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25AC0048 | Jun 11, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY NAMALPALAN, MAGSINGAL, ILOCOS SUR | Completed | ₱5.9M |
| 25AC0007 | Feb 21, 2025 | CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG PARSUA RIVER, PACKAGE 1, BARANGAY MARATUDO, MAGSINGAL, ILOCOS SUR | On-Going | ₱18.8M |
| 25AC0015 | Feb 21, 2025 | CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG PARSUA RIVER, BARANGAY MARATODO, MAGSINGAL, ILOCOS SUR | On-Going | ₱23.8M |
| 24AC0035 | Mar 15, 2024 | REHABILITATION OF ROAD, BARANGAY SAN RAMON, MAGSINGAL, ILOCOS SUR | Completed | ₱5.0M |
| 23AC0140 | Jan 5, 2024 | CONSTRUCTION OF FMR, BRGY. PATONG-LABUT, BRGY. PATONG-LABUT, MAGSINGAL, ILOCOS SUR | Completed | ₱9.6M |
| 23AC0081 | Oct 6, 2023 | REHABILITATION OF MAGSINGAL NORTH CENTRAL SCHOOL,BRGY. SANTA MONICA, MAGSINGAL, ILOCOS SUR | Completed | ₱4.9M |
| 23AC0063 | Jul 14, 2023 | CONSTRUCTION OF SOLAR WATER SYSTEM LEVEL II, MUNICIPALITY OF MAGSINGAL, ILOCOS SUR | Completed | ₱9.8M |
| 23AC0080 | Jun 14, 2023 | CONSTRUCTION OF MULTI-PURPOSE BUILDING. BRGY. MANZANTE, MAGSINGAL, ILOCOS SUR | Completed | ₱5.0M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.