Project 21A00173

DPWH infrastructure contract
Contract ID:
21A00173
Fingerprint:
bc0caca1959292…ba009a2392 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Aug 24, 2021 (5 yrs 2 mo ago) · Target/actual end Jan 21, 2022
Description:
CONSTRUCTION/UPGRADING/REHABILITATION OF DRAINAGE ALONG PANGASINAN-LA UNION INTER-PROVL ROAD, K0382+340-K0383+703 R/S
Category:
Roads
Implementing office:
DPWH Region I · Region I
Contractor:
ALCEL CONSTRUCTION · DPWH contractor code 15129
Contract amount:
₱14,407,435.39 (₱14.4M)
Funding source:
Regular Infra - GAA 2021 OO-1
Budget year:
2021

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
ffeeeaf24d1f…Aug 9, 2021DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - REGION I₱14,407,435.39

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25AH0126Jun 11, 2025CONSTRUCTION(COMPLETION)OF MULTI-PURPOSE BUILDING,BRGY. BUENLAG,MANGALDAN,PANGASINANOn-Going₱2.9M
25AH0130Jun 11, 2025CONSTRUCTION(COMPLETION)OF MULTI-PURPOSE BUILDING,BRGY. GUESANG,MANGALDAN,PANGASINANOn-Going₱1.9M
25AH0131Jun 11, 2025REHABILITATION OF ROAD, BARANGAY AMANSABINA,MANGALDAN, PANGASINANCompleted₱4.8M
25AH0173Mar 21, 2025CONCRETING OF BRGY. MALABAGO-BRGY.ALITAYA SERVICE ROAD FMR,BRGY. MALABAGO,MANGALDAN,PANGASINANCompleted₱14.4M
25AH0174Mar 21, 2025CONCRETING OF BRGY. SALAAN FMR,BRGY. SALAAN,MANGALDAN,PANGASINANCompleted₱14.5M
25AH0127Mar 20, 2025CONSTRUCTION(COMPLETION)OF MULTI-PURPOSE BUILDING,BRGY. POBLACION,MANGALDAN,PANGASINANCompleted₱1.9M
25A00286Feb 25, 2025WIDENING OF PERMANENT BRIDGES - EMBARCADERO BR. (B01329LZ) ALONG MANGALDAN-MANAOAG-BINALONAN RD (PHASE II)On-Going₱93.6M
25AH0077Feb 25, 2025CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY POBLACION, MANGALDAN, PANGASINANOn-Going₱3.9M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.