Project 21AD0113
DPWH infrastructure contract
Contract ID:
21AD0113
Fingerprint:
b62b43ddbae897…dc168e6d67 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Jun 18, 2021 (5 yrs 4 mo ago) · Target/actual end Sep 17, 2021
Description:
CONCRETING OF SITIO LINGGAWA BRGY. PIDPID FMR, BRGY. PIDPID, STA. CRUZ, ILOCOS SUR
Category:
Roads
Implementing office:
DPWH Ilocos Sur 2nd DEO · Region I
Contractor:
PRECIOUS CONSTRUCTION · DPWH contractor code 32995
Contract amount:
₱11,939,988.25 (₱11.9M)
Funding source:
Outside Infra - GAA 2021 DA FMR
Budget year:
2021
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 56d39c98071c… | Jun 8, 2021 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - ILOCOS SUR 2ND DEO | ₱11,575,378.58 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25AD0055 | May 23, 2025 | BIP-ACCESS ROAD AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-IMPROVEMENT OF ROAD, BRGY. VILLA HERMOSA, STA. CRUZ, ILOCOS SUR | Completed | ₱4.8M |
| 25AD0057 | May 22, 2025 | BIP-FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURE/FACILITIES-CONSTRUCTION OF BUAYA RIVER CONTROL, BRGY. VILLA HERMOSA, STA. CRUZ, ILOCOS SUR | Completed | ₱9.6M |
| 25A00422 | Apr 7, 2025 | CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, CONSTRUCTION OF STA. CRUZ FLOOD CONTROL, BRGY. VILLA HERMOSA, STA. CRUZ, ILOCOS SUR | On-Going | ₱28.4M |
| 25AD0077 | Mar 24, 2025 | CONCRETING OF BRGY. TAMPUGO - BRGY. BESALAN-SITIO UBBOG, BRGY. CAMANGAAN FMR, BRGY. TAMPUGO, STA. CRUZ, ILOCOS SUR | Completed | ₱14.5M |
| 25AD0078 | Mar 24, 2025 | CONCRETING OF BRGY. BUGBUGA -BRGY. COSCOSNONG FMR, BRGY. BUGBUGA, STA. CRUZ, ILOCOS SUR | Completed | ₱14.5M |
| 25AD0031 | Feb 10, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, SANTA CRUZ, ILOCOS SUR | On-Going | ₱9.7M |
| 24A00490 | Jul 22, 2024 | WIDENING OF PERMANENT BRIDGES - STA. CRUZ PARALLEL BR. (PHASE II) | Completed | ₱45.0M |
| 24A00505 | Jul 22, 2024 | BASIC INFRASTRUCTURE PROGRAM (BIP), CONSTRUCTION OF MULTI - PURPOSE BUILDING SAGAT ELEMENTARY SCHOOL, BARANGAY SAGAT, STA. CRUZ, ILOCOS SUR | Completed | ₱9.9M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.