Project 21BF0084
DPWH infrastructure contract
Contract ID:
21BF0084
Fingerprint:
2a826e69b7f5bc…9d231a911e Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Oct 19, 2021 (5 yrs ago) · Target/actual end May 2, 2022
Description:
MODIFIED STANDARD DPWH-DEPED CONSTRUCTION OF STANDARD TWO (2) STOREY SCHOOL BUILDING (2STY 4CL LAB), MINAGBAG INTEGRATED SCHOOL (SECONDARY), QUEZON, ISABELA
Category:
Buildings and Facilities
Implementing office:
DPWH Isabela 2nd DEO · Region II
Contractor:
RR BUILDERS · DPWH contractor code 38348
Contract amount:
₱12,032,908.06 (₱12.0M)
Funding source:
Outside Infra - GAA 2021 DepEd BEFF
Budget year:
2021
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| aff66970d0d6… | Sep 28, 2021 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - ISABELA 2ND DEO | ₱12,032,908.06 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 26BF0037 | Aug 3, 2026 | ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - BRIDGE PROGRAM - WIDENING OF PERMANENT BRIDGES - LAGUINDAY PARALLEL BR. ALONG SANTIAGO-TUGUEGARAO RD, RIZAL KALINGA | On-Going | ₱56.1M |
| 25BF0104 | Oct 13, 2025 | RAINWATER COLLECTOR SYSTEM 1. VICTORIA ELEMENTARY SCHOOL, AURORA, ISABELA 2. BURGOS NATIONAL HIGH SCHOOL, BURGOS, ISABELA 3. HARANA ELEMENTARY SCHOOL, LUNA, ISABELA 4. BIMONTON INTEGRATED SCHOOL, MALLIG, ISABELA 5. MANANO ELEMENTARY SCHOOL MAIN, MALLIG, | On-Going | ₱2.5M |
| 25BF0068 | Aug 6, 2025 | OO2: FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE, UPPER CHICO RIVER IRRIGATION SYSTEM, QUEZON, ISABELA | Completed | ₱14.0M |
| 25BF0089 | Aug 4, 2025 | CONSTRUCTION OF SCHOOL BUILDING, MINAGBAG INTEGRATED SCHOOL, QUEZON, ISABELA | Completed | ₱4.8M |
| 25BF0076 | Jul 9, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. SAN JUAN, QUEZON, ISABELA | Completed | ₱5.8M |
| 25BF0078 | Jul 9, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING (LEGISLATIVE BUILDING), BRGY. SAMONTE, QUEZON, ISABELA | Completed | ₱9.6M |
| 25BF0049 | Jun 30, 2025 | COMPLETION OF MULTI-PURPOSE BUILDING, BARANGAY TUROD, QUEZON, ISABELA | On-Going | ₱4.8M |
| 25BF0029 | Jun 16, 2025 | CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (LEGISLATIVE BUILDING), BARANGAY SAMONTE, QUEZON, ISABELA | On-Going | ₱4.9M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.