Project 21CD0011
DPWH infrastructure contract
Contract ID:
21CD0011
Fingerprint:
a31fc958242871…10e3467695 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Mar 8, 2021 (5 yrs 8 mo ago) · Target/actual end May 6, 2021
Description:
CONSTRUCTION OF ROAD, SITIO PIRE 2, STA. LUCIA, ANGAT, BULACAN
Category:
Roads
Implementing office:
DPWH Bulacan 2nd DEO · Region III
Contractor:
FORTUNE RDC ENTERPRISES · DPWH contractor code 41515
Contract amount:
₱1,918,324.27 (₱1.9M)
Funding source:
Regular Infra - GAA 2021 LP
Budget year:
2021
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 8aa6997649d4… | Feb 18, 2021 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - BULACAN 2ND DEO | ₱1,918,324.27 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25CP0140 | Jul 22, 2025 | CONVERGE. AND SPECIAL SUPPORT PROG. BASIC INFRA. PROG. (BIP) - BIP - FLOOD MITIGATION STRUCTS. PROTECTING MAJOR/STRATEGIC PUBLIC BLDGS./FACILITIES-CONST. OF FLOOD CONTROL STRUCT, SAN MIGUEL RIVER, BRGY. LABNE,SAN MIGUEL, BULACAN, PACKAGE 12 | On-Going | ₱97.4M |
| 25CP0043 | Jun 22, 2025 | FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-CONSTRUCTION OF BUGA-SALACOT CONCRETE SLOPE PROTECTION ALONG BULO RIVER SECTION, SAN MIGUEL,BULACAN (UPSTREAM DIKE,PACKAGE 1) | On-Going | ₱47.5M |
| 25CP0052 | Jun 22, 2025 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM - SPECIAL ROAD FUND - MOTOR VEHICLE USER'S CHARGE (MVUC) AS PER R.A. 11239- SOLAR STREET LIGHTS INSTALLATION AND APPLICATION, SIBUL- BIAK NA BATO ROAD SECTION, SAN MIGUEL, BULACAN | On-Going | ₱95.1M |
| 25CP0133 | Jun 22, 2025 | CONVERGE. AND SPECIAL SUPPORT PROG. - BASIC INFRA. PROG. (BIP) - BIP - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROADS LEADING TO MAJOR/ STRAT. PUBLIC BLDGS./ FACILITIES - REHAB. OF SIBUL - DRT ROAD, DONA REMEDIOS TRINIDAD, BULACAN (PHASE 2) | On-Going | ₱97.6M |
| 25CP0139 | Jun 22, 2025 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM- BASIC INFRA. PROGRAM (BIP)-BIP-FLOOD MITIGATION STRUCT. PROTECTING MAJOR/STRAT. PUBLIC BUILDINGS/FACILITIES - CONST. OF CONCRETE FLOOD CONTROL STRUCTURE, SAN MIGUEL RIVER, BRGY LABNE, SAN MIGUEL, BULACAN,PACKAGE 11 | On-Going | ₱97.5M |
| 25CP0145 | Jun 22, 2025 | CONVERGE. AND SPECIAL SUPPORT PROG. - BASIC INFRA.PROG. (BIP) - BIP - FLOOD MITIGATION STRUCTS. PROTECTING MAJOR/ STRATEGIC PUBLIC BLDGS./ FACILITIES - CONST. OF FLOOD CONTROL STRUCTS,. SAN MIGUEL RIVER, BRGY. LABNE, SAN MIGUEL, BULACAN, (PACKAGE 13) | On-Going | ₱97.5M |
| 25CP0149 | Jun 22, 2025 | BASIC INFRASTRUCTURE PROGRAM (BIP) - BIP - FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION OF CONCRETE SLOPE PROTECTION INCL. IMPROVEMENT OF WATERWAYS ALONG TARTARO SECTION, SAN MIGUEL, BULACAN (PHASE 6) | On-Going | ₱97.4M |
| 25CP0154 | Jun 22, 2025 | CONVERGE. AND SPECIAL SUPPORT PROG. -BASIC INFRA. PROG. (BIP) - BIP -FLOOD MITIGATION STRUCTS. PROTECTING MAJOR/ STRAT. PUBLIC BLDGS./ FACILITIES - CONSTRUCTION OF CONCRETE SLOPE PROTECTION INCL. IMPROVEMENT OF WATERWAYS ALONG TARTARO SECTION, SAN MIGUEL | On-Going | ₱48.8M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.