Project 21CE0124
DPWH infrastructure contract
Contract ID:
21CE0124
Fingerprint:
76e7a2bab8a6cc…e5e90711ab Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Feb 16, 2021 (5 yrs 8 mo ago) · Target/actual end Dec 2, 2021
Description:
CONSTRUCTION OF FLOOD CONTROL STRUCTURES ALONG TALAVERA RIVER, STA. 43+370.50-STA. 43+720.50, BRGY. VILLA VINIEGAS, LLANERA, NUEVA ECIJA
Category:
Flood Control and Drainage
Implementing office:
DPWH Nueva Ecija 1st DEO · Region III
Contractor:
IRC CONSTRUCTION & SUPPLIES (29943) / SYMMETRICON BUILDERS CORP. · DPWH contractor code 37555
Contract amount:
₱45,065,089.77 (₱45.1M)
Funding source:
Regular Infra - GAA 2021 OO-2
Budget year:
2021
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25CE0195 | Jun 30, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY GEN. RICARTE, LLANERA, NUEVA ECIJA | Completed | ₱5.9M |
| 25CE0196 | Jun 30, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY VICTORIA, LLANERA, NUEVA ECIJA | Completed | ₱4.9M |
| 25CE0256 | Mar 25, 2025 | ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - TERTIARY ROADS, JCT PINAGPANAAN-RIZAL-PANTABANGAN RD - K0136 + 000 - K0137 + 000 | Completed | ₱14.7M |
| 25CE0109 | Mar 20, 2025 | REHABILITATION OF ROAD, BARANGAY SANTA BARBARA TO BARANGAY VILLA VINIEGAS, LLANERA, NUEVA ECIJA | Completed | ₱9.7M |
| 25CE0140 | Feb 17, 2025 | CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY BAGUMBAYAN, LLANERA, NUEVA ECIJA | Completed | ₱3.9M |
| 25CE0102 | Feb 14, 2025 | CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY VICTORIA, LLANERA, NUEVA ECIJA | Completed | ₱4.7M |
| 25CE0112 | Feb 14, 2025 | CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY PLARIDEL, LLANERA, NUEVA ECIJA | Completed | ₱4.0M |
| 25CE0113 | Feb 11, 2025 | CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY SAN FRANCISCO, LLANERA, NUEVA ECIJA | Completed | ₱2.5M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.