Project 21CE0189
DPWH infrastructure contract
Contract ID:
21CE0189
Fingerprint:
88ab6cb01728a5…f13c813a35 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Sep 15, 2021 (5 yrs 1 mo ago) · Target/actual end Nov 22, 2021
Description:
CONSTRUCTION/COMPLETION (2STY6CL), PAITAN SUR ES, CUYAPO, NUEVA ECIJA
Category:
Buildings and Facilities
Implementing office:
DPWH Nueva Ecija 1st DEO · Region III
Contractor:
KEVIN PAUL CONSTRUCTION · DPWH contractor code 49090
Contract amount:
₱24,750,010.95 (₱24.8M)
Funding source:
Outside Infra - GAA 2021 DepEd BEFF
Budget year:
2021
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| ea0bda4d28c0… | Sep 7, 2021 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - NUEVA ECIJA 1ST DE | ₱24,750,010.95 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 24CE0364 | Jul 1, 2025 | CONSTRUCTION (COMPLETION) OF DRAINAGE STRUCTURE, BARANGAY SAN JOSE, CUYAPO, NUEVA ECIJA | Completed | ₱1.9M |
| 25CJ0245 | Jun 20, 2025 | CONSTRUCTION OF MONCADA - SAN MANUEL BYPASS ROAD (SEGMENT 6), TARLAC | On-Going | ₱96.5M |
| 25CJ0257 | Jun 20, 2025 | CONSTRUCTION OF MONCADA - SAN MANUEL BYPASS ROAD (SEGMENT 7), TARLAC | On-Going | ₱96.5M |
| 25CE0269 | Jun 9, 2025 | CONSTRUCTION OF ROAD, BARANGAY BIBICLAT, CUYAPO, NUEVA ECIJA | Completed | ₱4.8M |
| 25CE0288 | Jun 9, 2025 | CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BRGY. COLOSBOA, CUYAPO, NUEVA ECIJA | Completed | ₱5.4M |
| 25CE0131 | Jun 2, 2025 | CONSTRUCTION OF ROAD, BARANGAY SABIT, CUYAPO, NUEVA ECIJA | Completed | ₱4.9M |
| 25CE0284 | Jun 2, 2025 | CONSTRUCTION OF SCHOOL BUILDING, STA. CLARA ELEMENTARY SCHOOL, BARANGAY STA. CLARA, CUYAPO, NUEVA ECIJA | Completed | ₱4.9M |
| 25CE0301 | Jun 2, 2025 | CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BRGY. MALBEG, CUYAPO, NUEVA ECIJA | Completed | ₱3.9M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.