Project 21CJ0019
DPWH infrastructure contract
Contract ID:
21CJ0019
Fingerprint:
3f6c5bccc98bf8…98b81f5c4d Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Mar 2, 2021 (5 yrs 8 mo ago) · Target/actual end May 1, 2021
Description:
LOCAL INFRASTRUCTURE PROGRAM CONSTRUCTION OF BARANGAY ROAD IN BARANGAY SAN JUAN, MONCADA, TARLAC
Category:
Roads
Implementing office:
DPWH Tarlac DEO · Region III
Contractor:
EDUARDO T. SANTOS CONSTRUCTION & SUPPLIES · DPWH contractor code 34005
Contract amount:
₱4,700,986.87 (₱4.7M)
Funding source:
Regular Infra - GAA 2021 LP
Budget year:
2021
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 4d6d41ba75bd… | Feb 18, 2021 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - TARLAC 1ST DEO | ₱4,700,986.87 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25CJ0192 | Jun 20, 2025 | REHABILITATION OF CAMPOSANTO 1 - NORTE - TUBECTUBANG ROAD (SEGMENT 3), MONCADA, TARLAC | Completed | ₱96.5M |
| 25CJ0238 | Jun 20, 2025 | CONSTRUCTION OF MONCADA - PANIQUI DIVERSION ROAD (SEGMENT 5), MONCADA, TARLAC | On-Going | ₱96.5M |
| 25CJ0081 | May 22, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), BARANGAY CAPAOAYAN, MONCADA, TARLAC | Completed | ₱4.9M |
| 25CJ0210 | May 22, 2025 | INSTALLATION OF ROAD SAFETY DEVICES AND SOLAR LED STREET LIGHTS ALONG CAMPOSANTO 1 - NORTE - TUBECTUBANG ROAD TO MANILA NORTH RD (ANNEX 2), MONCADO, TARLAC | Completed | ₱47.3M |
| 25CJ0212 | May 22, 2025 | INSTALLATION OF ROAD SAFETY DEVICES AND SOLAR LED STREET LIGHTS ALONG MONCADA-PANIQUI DIVERSION RD TO MANILA NORTH RD (ANNEX 2), TARLAC | Completed | ₱47.4M |
| 25CJ0163 | May 16, 2025 | CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BAKET-BAKET RIVER (ANNEX 8), MONCADA, TARLAC | On-Going | ₱96.5M |
| 25CJ0226 | May 16, 2025 | IMPROVEMENT OF MONCADA ROAD NETWORK (ANNEX 2), MONCADA, TARLAC | Completed | ₱29.7M |
| 25CJ0161 | Apr 8, 2025 | CONSTRUCTION OF FLOOD CONTROL STRUCTURES ALONG BAKET - BAKET RIVER, MONCADA, TARLAC (SEGMENT 14) | Completed | ₱74.3M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.