Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 21CJ0159

DPWH infrastructure contract
Contract ID:
21CJ0159
Fingerprint:
e47712c46da8b0…61198f5c4a Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Mar 31, 2022 (4 yrs 7 mo ago) · Target/actual end Jun 13, 2022
Description:
CONSTRUCTION / REPAIR / REHABILITATION / IMPROVEMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS CONSTRUCTION OF STA. IGNACIA-MAYANTOC DIVERSION ROAD, TARLAC
Category:
Roads
Implementing office:
DPWH Tarlac DEO · Region III
Contract amount:
₱9,602,659.62 (₱9.6M)
Funding source:
Regular Infra - GAA 2021 LP
Budget year:
2021

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
7b8dd3e756f9…Mar 21, 2022DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - TARLAC 1ST DEO₱9,602,659.62

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
26CJ0122Jul 13, 2026PREVENTIVE MAINTENANCE ROMULO H-WAY - K0128 + 825 - K0129 + 990On-Going₱52.7M
25CJ0235Jun 20, 2025CONSTRUCTION OF STA. IGNACIA - MAYANTOC DIVERSION ROAD (SEGMENT 1), TARLACOn-Going₱95.5M
25CJ0239Jun 20, 2025CONSTRUCTION OF STA. IGNACIA - CAMILING DIVERSION ROAD (SEGMENT 4), TARLACCompleted₱96.5M
25CJ0261Jun 20, 2025CONSTRUCTION OF STO. DOMINGO - LAWACAMULAG DIVERSION ROAD (SEGMENT 3), TARLACOn-Going₱95.5M
25CJ0167May 16, 2025PREVENTIVE MAINTENANCE ROMULO H- WAY - K0137 + 920 - K0139 + 410Completed₱96.5M
25CJ0199Apr 8, 2025REHABILITATION OF STA. IGNACIA ROAD NETWORK (ANNEX 2), STA. IGNACIA, TARLACCompleted₱99.0M
25CJ0139Mar 24, 2025ROAD WIDENING ROMULO H-WAY - K0150 + 192 - K0150 + 330Completed₱15.5M
25CJ0111Mar 14, 2025INSTALLATION/APPLICATION OF ROAD SAFETY FACILITIES (ROADWAY LIGHTING) ALONG ROMULO H-WAY - K0139 + 968 - K0144 + 050Completed₱39.8M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.