Project 21CL0090
DPWH infrastructure contract
Contract ID:
21CL0090
Fingerprint:
4d9aef814655fa…39eb653f54 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Sep 24, 2021 (5 yrs 1 mo ago) · Target/actual end Nov 17, 2022
Description:
CONSTRUCTION OF MISSING LINKS/NEW ROADS STA.CRUZ- MANGATAREM ROAD (ZAMBALES SIDE, PHASE 8) STA. CRUZ, ZAMBALES
Category:
Roads
Implementing office:
DPWH Zambales 1st DEO · Region III
Contractor:
R.D. TALENS CONSTRUCTION AND TRADING · DPWH contractor code 36817
Contract amount:
₱81,927,293.09 (₱81.9M)
Funding source:
Regular Infra - GAA 2021 OO-1
Budget year:
2021
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 4cf70efa2759… | Sep 20, 2021 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - ZAMBALES 1ST DEO | ₱74,479,452.04 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25CL0101 | Jul 7, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. GUINABON, STA CRUZ, ZAMBALES | On-Going | ₱17.6M |
| 25CL0105 | Jul 7, 2025 | COMPLETION OF MULTI-PURPOSE BUILDING, BRGY. SOUTH POBLACION, STA. CRUZ, ZAMBALES | On-Going | ₱13.7M |
| 25CL0199 | Jul 7, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, SITIO ACOJE, BRGY. LUCAPON SOUTH, STA. CRUZ, ZAMBALES | On-Going | ₱16.6M |
| 25CL0206 | Jul 7, 2025 | CONSTRUCTION OF WATER SYSTEM, BRGY. LUCAPON SOUTH, STA. CRUZ, ZAMBALES | On-Going | ₱9.9M |
| 25CL0222 | May 28, 2025 | CONSTRUCTION OF WATER SUPPLY SYSTEM, BARANGAY BOLITOC, SANTA CRUZ, ZAMBALES | On-Going | ₱9.9M |
| 25CL0226 | May 23, 2025 | CONSTRUCTION OF ACCESS ROAD/ DIVERSION ROAD INCLUDING DRAINAGE STRUCTURE, DAAN KALIKASAN TO UACON, PHASE 2, SANTA CRUZ, ZAMBALES | On-Going | ₱95.3M |
| 25CL0227 | May 23, 2025 | CONSTRUCTION OF ACCESS ROAD/ DIVERSION ROAD INCLUDING DRAINAGE STRUCTURE, DAAN KALIKASAN TO UACON, PHASE 3, SANTA CRUZ, ZAMBALES | On-Going | ₱95.3M |
| 25CL0077 | Apr 3, 2025 | CONSTRUCTION OF RIVERBANK PROTECTION STRUCTURE ALONG BAYTO RIVER, PHASE 10, SANTA CRUZ, ZAMBALES | On-Going | ₱96.5M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.