Project 21CN0039
DPWH infrastructure contract
Contract ID:
21CN0039
Fingerprint:
e5cca5567473b3…30f3a69140 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Mar 2, 2021 (5 yrs 8 mo ago) · Target/actual end Jul 20, 2021
Description:
CONSTRUCTION OF EVACUATION CENTER, BRGY. GUPA, DIPACULAO, AURORA
Category:
Buildings and Facilities
Implementing office:
DPWH Aurora DEO · Region III
Contractor:
MORNING STEEL CONSTRUCTION · DPWH contractor code 30698
Contract amount:
₱7,682,361.46 (₱7.7M)
Funding source:
Regular Infra - GAA 2021 LP
Budget year:
2021
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| a28c2edf0e23… | Feb 18, 2021 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - AURORA DEO | ₱7,682,361.46 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25CN0028 | May 28, 2025 | REHABILITATION/MAJOR REPAIR OF PERMANENT BRIDGES, DIOS BR. (B03279LZ) ALONG BALER - CASIGURAN RD (DINADIAWAN - CASIGURAN SECT) | On-Going | ₱4.9M |
| 25CN0030 | May 28, 2025 | REHABILITATION/MAJOR REPAIR OF PERMANENT BRIDGES, PUGO BR. (B03278LZ) ALONG BALER - CASIGURAN RD (DINADIAWAN - CASIGURAN SECT) | On-Going | ₱4.9M |
| 25CN0118 | May 26, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), BARANGAY 2, CASIGURAN, AURORA | Completed | ₱6.9M |
| 25CN0142 | May 26, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY ESTEVES, CASIGURAN, AURORA | Completed | ₱5.0M |
| 25CN0140 | May 23, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY DITINAGYAN, CASIGURAN, AURORA | Completed | ₱5.0M |
| 25CN0145 | May 23, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY LUAL, CASIGURAN, AURORA | Completed | ₱5.0M |
| 25C00004 | Apr 8, 2025 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM-SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONSTRUCTION OF CASALOGAN FLOOD CONTROL STRUCTURE, CASIGURAN, AURORA | On-Going | ₱141.9M |
| 25CN0078 | Apr 3, 2025 | CONSTRUCTION OF ROAD, BARANGAY DIBACONG, CASIGURAN, AURORA | On-Going | ₱9.7M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.