Project 21CN0054

DPWH infrastructure contract
Contract ID:
21CN0054
Fingerprint:
82a508bde58332…bd81cc4b6f Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Mar 2, 2021 (5 yrs 8 mo ago) · Target/actual end Nov 19, 2021
Description:
CONSTRUCTION OF SEA WALL IN SITIO CASTILLO, BARANGAY SABANG, BALER, AURORA
Category:
Flood Control and Drainage
Implementing office:
DPWH Aurora DEO · Region III
Contractor:
MORNING STEEL CONSTRUCTION · DPWH contractor code 30698
Contract amount:
₱29,700,000.00 (₱29.7M)
Funding source:
Regular Infra - GAA 2021 LP
Budget year:
2021

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
36255ec752a7…Feb 18, 2021DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - AURORA DEO₱24,500,000.00

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25CN0157Sep 1, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING , BARANGAY ZABALI, BALER, AURORAOn-Going₱99.0M
25CN0166Aug 27, 2025CONSTRUCTION OF ROAD (PHASE 2), BARANGAY ZABALI, BALER, AURORATerminated₱0
25CN0096Aug 4, 2025CONSTRUCTION OF ROAD, BARANGAY ZABALI, BALER, AURORACompleted₱28.9M
25CN0168Jul 18, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING (DAY CARE CENTER), BARANGAY CALABUANAN, BALER, AURORAOn-Going₱4.8M
25CN0116Jul 7, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING (BARANGAY HALL), BARANGAY RESERVA, BALER, AURORAOn-Going₱6.9M
25CN0182Jul 3, 2025RAINWATER COLLECTOR SYSTEMOn-Going₱2.6M
25CN0150Jun 10, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY SABANG, BALER, AURORAOn-Going₱4.9M
25CN0021May 28, 2025REPLACEMENT OF PERMANENT WEAK BRIDGES, PUDOC BR. (B03014LZ) ALONG BALER - CASIGURAN RD (BALER - DINADIAWAN)On-Going₱65.7M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.